Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    07/20/2009
Contract ID: 090353   Estimate Number: 0001     Contract No: 411226
Residency: CIRCUIT ENGR. DISTRICT # 8 (06009)   Estimate Type: Progressive     Account No: 432600

Project Number(s): STP-STIM(224)CO
Primary Job Piece No: 18949(04)
Contract Description: SURFACING (ASPHALT) COUNTY ROAD (NS-271): FROM SH-45, 1.0 MILE WEST OF GOLTRY, EXTEND NORTH. PROJECT LENGTH = 2.171 MILES
Primary County: ALFALFA              
Name of Road: COUNTY ROAD(NS-271)              
Prime Contractor: THE CUMMINS CONSTRUCTION CO., INC.              
    P. O. BOX 748              
    ENID , OK   73702              
Surety Company: HARTFORD ACCIDENT & INDEMNITY COMPANY              

Date Let: 04/23/2009 NTP Effective Date: 08/03/2009 Pay Period: 05/15/2009  TO  07/15/2009
Date Awarded: 04/27/2009 Date Work Began: Original Contract Time: 60
Date Contract Executed: 05/13/2009 Date Time Stopped: Current Time Charged: 10.00
Date NTP Issued: 05/15/2009 Completion Date: Current Time Allowed: 60.00
General Liability Expires: 09/01/2009 Workman's Comp Expires: 01/01/1010 Percent Time Used: 16.67 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $815,939.30 Total to Date Prev to Date This Estimate
Bid Amount: $815,939.30 Participating: $375,433.77 $0.00 $375,433.77
Percent Complete: 45.92 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $441,244.41 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $441,244.41 Total Earnings: $375,433.77 $0.00 $375,433.77
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $375,433.77 $0.00 $375,433.77
Other Adjustments: $-738.88 $0.00 $-738.88
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $374,694.89 $0.00 $374,694.89

Estimate Adjustment Detail

Contract ID: 090353   Estimate Number: 0001     Primary JP: 18949(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
18949(04) 0011 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-738.88
Subtotals For Line Item Adjustments $-738.88


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090353   Estimate Number: 0001     Primary JP: 18949(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(224)CO Project:    18949(04) Category:    0100/ROADWAY
0001 EARTHWORK 202(G) 0185 LSUM 1.000 1.000   0.000 $15,600.00 $0.00 $0.00
0002 TEMPORARY SILT FENCE 223 2801 LF 1,000.000 1,000.000   0.000 $1.75 $0.00 $0.00
0003 TEMPORARY SILT DIKE 227 0100 LF 200.000 200.000   0.000 $8.20 $0.00 $0.00
0004 SOLID SLAB SODDING 230(A) 2806 SY 7,018.000 7,018.000   0.000 $1.90 $0.00 $0.00
0005 VEGETATIVE MULCHING 233(A) 2817 AC 1.450 1.450   0.000 $545.00 $0.00 $0.00
0006 PROCESSING EXISTING BASE & SURFACE, METHOD A 311(A) 0151 STA 13.000 13.000 13.050 13.050 $1,110.00 $14,485.50 $14,485.50
0007 (SP)FLY ASH 327(A) 4200 TON 358.000 358.000 93.410 93.410 $60.50 $5,651.31 $5,651.31
0008 (SP)CEMENTITIOUS STABILIZED SUBGRADE 327(E) 4240 SY 3,500.000 3,500.000 3,190.000 3,190.000 $4.50 $14,355.00 $14,355.00
0009 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 72.000 72.000   0.000 $36.25 $0.00 $0.00
0010 TACK COAT 407 0250 GAL 2,627.000 2,627.000 975.000 975.000 $3.45 $3,363.75 $3,363.75
0011 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 6,600.000 6,600.000 4,785.520 4,785.520 $65.30 $312,494.46 $312,494.46
0012 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 3,300.000 3,300.000   0.000 $72.10 $0.00 $0.00
0013 TRAFFIC STRIPE(PAINT)(4" WIDE) 854(A) 8800 LF 34,071.000 34,071.000   0.000 $0.10 $0.00 $0.00
0014 TRAFFIC STRIPE(PAINT)(WORDS) 854(B) 8806 EA 4.000 4.000   0.000 $92.65 $0.00 $0.00
0015 TRAFFIC STRIPE(PAINT)(SYMBOLS) 854(B) 8809 EA 2.000 2.000   0.000 $272.50 $0.00 $0.00
0016 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.500 0.500 $4,905.00 $2,452.50 $2,452.50
Subtotals For Category     0100/ROADWAY    $352,802.52 $352,802.52
Fed/State Project Number:    STP-STIM(224)CO Project:    18949(04) Category:    0600/STAKING
0017 STAKING 642 0098 LSUM 1.000 1.000 0.750 0.750 $8,175.00 $6,131.25 $6,131.25
Subtotals For Category     0600/STAKING    $6,131.25 $6,131.25
Fed/State Project Number:    STP-STIM(224)CO Project:    18949(04) Category:    0640/CONSTRUCTION
0018 MOBILIZATION 641 1399 LSUM 1.000 1.000 0.500 0.500 $33,000.00 $16,500.00 $16,500.00
Subtotals For Category     0640/CONSTRUCTION    $16,500.00 $16,500.00
Subtotals For Project STP-STIM(224)CO /18949(04) $375,433.77 $375,433.77