Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    12/16/2009
Contract ID: 090334   Estimate Number: 0009     Contract No: 411212
Residency: CIRCUIT ENGR. DISTRICT # 7 (05005)   Estimate Type: Progressive     Account No: 434500

Project Number(s): BRO-STIM(222)CO
Primary Job Piece No: 23064(04)
Contract Description: BRIDGE AND APPROACHES COUNTY ROAD (NS-189): OVER UNNAMED CREEK, 5.5 MILES WEST AND 3.0 MILES SOUTH OF WILLOW. PROJECT LENGTH = 0.150 MILES
Primary County: GREER              
Name of Road: COUNTY ROAD (NS-189)              
Prime Contractor: K & R BUILDERS, INC.              
    P.O. BOX 656              
    WHEATLAND , OK   73097              
Surety Company: OHIO CASUALTY INSURANCE COMPANY              

Date Let: 04/23/2009 NTP Effective Date: 10/05/2009 Pay Period: 12/01/2009  TO  12/15/2009
Date Awarded: 04/27/2009 Date Work Began: 08/12/2009 Original Contract Time: 90
Date Contract Executed: 05/08/2009 Date Time Stopped: Current Time Charged: 126.00
Date NTP Issued: 05/11/2009 Completion Date: Current Time Allowed: 127.00
General Liability Expires: 05/01/2010 Workman's Comp Expires: 07/01/2010 Percent Time Used: 99.21 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $363,750.26 Total to Date Prev to Date This Estimate
Bid Amount: $363,750.26 Participating: $346,893.43 $344,478.73 $2,414.70
Percent Complete: 95.37 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $16,856.83 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $16,856.83 Total Earnings: $346,893.43 $344,478.73 $2,414.70
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $346,893.43 $344,478.73 $2,414.70
Other Adjustments: $0.00 $-11,800.00 $11,800.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $346,893.43 $332,678.73 $14,214.70

Estimate Adjustment Detail

Contract ID: 090334   Estimate Number: 0009     Primary JP: 23064(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
23064(04) 0009 PC BR ITM FABS (AML) Stockpiled Material Initial Payment 0001 $30,082.52
23064(04) 0009 PC BR ITM FABS (AML) Stockpiled Material Adjustment 0004 $-30,082.52
23064(04) 0010 RSTL FABS (AML) Stockpiled Material Initial Payment 0002 $735.06
23064(04) 0010 RSTL FABS (AML) Stockpiled Material Adjustment 0005 $-735.06
23064(04) 0014 RSTL FABS (AML) Stockpiled Material Closure 0004 $-4,504.24
23064(04) 0014 RSTL FABS (AML) Stockpiled Material Adjustment 0003 $-1,362.22
23064(04) 0014 RSTL FABS (AML) Stockpiled Material Adjustment 0002 $-930.23
23064(04) 0014 RSTL FABS (AML) Stockpiled Material Initial Payment 0002 $6,796.69
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
23064(04) 0020 TYPE I-A FILTER BLANKET * Material Discrepancy Adjustments 0003 -28.71 $29.25 $-839.77
23064(04) 0020 TYPE I-A FILTER BLANKET * Material Discrepancy Adjustments 0004 28.71 $29.25 $839.77
23064(04) 0022 GUARD RAIL ANCHOR UNIT (TYPE II) * Material Discrepancy Adjustments 0008 -4.00 $2,950.00 $-11,800.00
23064(04) 0022 GUARD RAIL ANCHOR UNIT (TYPE II) * Material Discrepancy Adjustments 0009 4.00 $2,950.00 $11,800.00
Subtotals For Line Item Adjustments $0.00
* = User applied Line Item Adjustments


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090334   Estimate Number: 0009     Primary JP: 23064(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    BRO-STIM(222)CO Project:    23064(04) Category:    0100/ROADWAY
0001 EARTHWORK 202(G) 0185 LSUM 1.000 1.000   1.000 $32,800.00 $0.00 $32,800.00
0002 TEMPORARY SILT FENCE 223 2801 LF 880.000 880.000   681.950 $3.00 $0.00 $2,045.85
0003 SOLID SLAB SODDING 230(A) 2806 SY 6,200.000 6,200.000 928.730 5,268.730 $2.60 $2,414.70 $13,698.70
0004 VEGETATIVE MULCHING 233(A) 2817 AC 1.830 1.830   0.000 $1,000.00 $0.00 $0.00
0005 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 430.000 430.000   439.140 $28.00 $0.00 $12,295.92
0006 CLASS C CONCRETE 509(D) 0325 CY 11.300 11.300   0.000 $280.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY    $2,414.70 $60,840.47
Fed/State Project Number:    BRO-STIM(222)CO Project:    23064(04) Category:    0200/BRIDGE 'A'
0007 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 78.000 78.000   78.000 $15.00 $0.00 $1,170.00
0008 UNCLASSIFIED BACKFILL 501(D) 6353 CY 64.000 64.000   64.000 $20.00 $0.00 $1,280.00
0009 PRESTRESSED CONCRETE BEAMS (TYPE III) 503(A) 1312 LF 296.670 296.670   296.670 $188.00 $0.00 $55,773.96
0010 CONCRETE RAIL (TR1) 504(E) 1380 LF 207.000 207.000   207.000 $68.00 $0.00 $14,076.00
0011 STRUCTURAL STEEL 506(A) 1322 LB 1,620.000 1,620.000   1,620.000 $3.75 $0.00 $6,075.00
0012 CLASS AA CONCRETE 509(A) 1326 CY 58.300 58.300   58.300 $545.00 $0.00 $31,773.50
0013 CLASS A CONCRETE 509(B) 1328 CY 48.800 48.800   48.800 $575.00 $0.00 $28,060.00
0014 REINFORCING STEEL 511(A) 1332 LB 19,942.000 19,942.000   19,942.000 $0.90 $0.00 $17,947.80
0015 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 148.000 148.000   148.000 $40.00 $0.00 $5,920.00
0016 PILES, FURNISHED (HP 12X53) 514(A) 6011 LF 360.000 360.000   360.000 $50.00 $0.00 $18,000.00
0017 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 148.000 148.000   140.290 $10.00 $0.00 $1,402.90
0018 PILES, DRIVEN (HP 12X53) 514(B) 6294 LF 360.000 360.000   295.190 $10.00 $0.00 $2,951.90
0019 TYPE I-A PLAIN RIPRAP 601(A-1)1353 TON 1,250.000 1,250.000   1,082.190 $36.00 $0.00 $38,958.84
0020 TYPE I-A FILTER BLANKET 601(A-2)1355 TON 400.000 400.000   375.660 $29.25 $0.00 $10,988.06
0021 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   1.000 $6,500.00 $0.00 $6,500.00
0022 GUARD RAIL ANCHOR UNIT (TYPE II) 623(F) 6033 EA 4.000 4.000 0.000 4.000 $2,950.00 $0.00 $11,800.00
0023 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $4,000.00 $0.00 $4,000.00
Subtotals For Category     0200/BRIDGE 'A'    $0.00 $256,677.96
Fed/State Project Number:    BRO-STIM(222)CO Project:    23064(04) Category:    0600/STAKING
0024 STAKING 642 0098 LSUM 1.000 1.000   1.000 $6,000.00 $0.00 $6,000.00
Subtotals For Category     0600/STAKING    $0.00 $6,000.00
Fed/State Project Number:    BRO-STIM(222)CO Project:    23064(04) Category:    0640/CONSTRUCTION
0025 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.750 $6,500.00 $0.00 $4,875.00
0026 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $18,500.00 $0.00 $18,500.00
Subtotals For Category     0640/CONSTRUCTION    $0.00 $23,375.00
Subtotals For Project BRO-STIM(222)CO /23064(04) $2,414.70 $346,893.43