Contract ID: | 090309 | Estimate Number: | 0010 | Contract No: | 411073 | |||
Residency: | MCALESTER (02400) | Estimate Type: | Progressive | Account No: | 400200 | |||
Project Number(s): | NH-STIM(178)3R, NH-STIM(179)3R, NH-STIM(150)3R | ||||||||||||
Primary Job Piece No: | 26344(04) | ||||||||||||
Contract Description: | RESURFACE (CONCRETE) US-69: BEGIN 1.4 MILES NORTH OF SH-75W AND EXTEND NORTH. US-69: AT VARIOUS LOCATIONS IN PITTSBURG COUNTY. PROJECT LENGTH = 12.81 MILES | ||||||||||||
Primary County: | ATOKA | ||||||||||||
Name of Road: | US-69 | ||||||||||||
Prime Contractor: | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | ||||||||||||
P.O. BOX 3788 | |||||||||||||
EDMOND , OK 73083 | |||||||||||||
Surety Company: | LIBERTY MUTUAL INSURANCE COMPANY | ||||||||||||
Date Let: | 03/19/2009 | NTP Effective Date: | 04/20/2009 | Pay Period: | 08/26/2009 TO 08/31/2009 |
Date Awarded: | 03/30/2009 | Date Work Began: | 04/21/2009 | Original Contract Time: | 180 |
Date Contract Executed: | 04/02/2009 | Date Time Stopped: | Current Time Charged: | 134.00 | |
Date NTP Issued: | 04/03/2009 | Completion Date: | Current Time Allowed: | 187.00 | |
General Liability Expires: | 03/01/2010 | Workman's Comp Expires: | 03/01/2010 | Percent Time Used: | 71.66 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $5,343,785.64 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $5,343,785.64 | Participating: | $5,325,185.54 | $5,275,266.56 | $49,918.98 | ||
Percent Complete: | 99.65 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $18,600.10 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $18,600.10 | Total Earnings: | $5,325,185.54 | $5,275,266.56 | $49,918.98 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $5,325,185.54 | $5,275,266.56 | $49,918.98 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $5,325,185.54 | $5,275,266.56 | $49,918.98 |
Contract ID: | 090309 | Estimate Number: | 0010 | Primary JP: | 26344(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Change Order replacing Special Provision 108-STIM1(a-f) 99 | Approved | 05/05/2009 | 0.0 | $0.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 090309 | Estimate Number: | 0010 | Primary JP: | 26344(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: NH-STIM(178)3R | Project: 26296(04) | Category: 0100/ROADWAY NH-STIM(178)3R | ||||||||
0001 | (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 414(A1) 5725 | SY | 46,300.000 | 46,300.000 | 45,820.670 | $7.75 | $0.00 | $355,110.20 | |
0002 | P.C. CONCRETE FOR PAVEMENT | 414(I) 5275 | CY | 13,050.000 | 13,050.000 | 13,446.190 | $86.00 | $0.00 | $1,156,372.34 | |
0003 | P.C. CONCRETE PAVEMENT(PLACEMENT ONLY) | 414(J) 5400 | SY | 19,000.000 | 19,000.000 | 15,865.230 | $5.30 | $0.00 | $84,085.72 | |
0004 | COLD MILLING PAVEMENT | 417 5267 | SY | 53,350.000 | 53,350.000 | 52,869.990 | $0.75 | $0.00 | $39,652.50 | |
0005 | INLET (SMD-TYPE 2) | 611(E) 6002 | EA | 1.000 | 1.000 | 0.000 | 1.000 | $2,066.50 | $0.00 | $2,066.50 |
0006 | 18" R.C.PIPE CLASS III | 613(B) 0491 | LF | 18.000 | 18.000 | 0.000 | 16.000 | $34.48 | $0.00 | $551.68 |
Subtotals For Category 0100/ROADWAY NH-STIM(178)3R | $0.00 | $1,637,838.94 | ||||||||
Fed/State Project Number: NH-STIM(178)3R | Project: 26296(04) | Category: 0300/TRAFFIC NH-STIM(178)3R | ||||||||
0007 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 854(A) 8800 | LF | 16,000.000 | 16,000.000 | 15,750.000 | $0.07 | $0.00 | $1,102.50 | |
0008 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 854(C) 8530 | LF | 32,000.000 | 32,000.000 | 31,180.000 | 31,180.000 | $0.38 | $11,848.40 | $11,848.40 |
0009 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | 854(C) 8535 | LF | 10,600.000 | 10,600.000 | 8,640.000 | 8,640.000 | $0.39 | $3,369.60 | $3,369.60 |
0010 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 16,000.000 | 16,000.000 | 15,822.000 | $0.12 | $0.00 | $1,898.64 | |
0011 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.660 | $10,500.00 | $0.00 | $6,930.00 | |
Subtotals For Category 0300/TRAFFIC NH-STIM(178)3R | $15,218.00 | $25,149.14 | ||||||||
Subtotals For Project NH-STIM(178)3R /26296(04) | $15,218.00 | $1,662,988.08 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: NH-STIM(179)3R | Project: 26296(05) | Category: 0100/ROADWAY NH-STIM(179)3R | ||||||||
0012 | P.C. CONCRETE FOR PAVEMENT | 414(I) 5275 | CY | 17,500.000 | 17,500.000 | 0.000 | 17,255.210 | $86.00 | $0.00 | $1,483,948.06 |
0013 | P.C. CONCRETE PAVEMENT(PLACEMENT ONLY) | 414(J) 5400 | SY | 114,000.000 | 114,000.000 | 113,447.230 | $5.30 | $0.00 | $601,270.31 | |
0014 | COLD MILLING PAVEMENT | 417 5267 | SY | 100,000.000 | 100,000.000 | 90,373.520 | $0.75 | $0.00 | $67,780.16 | |
Subtotals For Category 0100/ROADWAY NH-STIM(179)3R | $0.00 | $2,152,998.53 | ||||||||
Fed/State Project Number: NH-STIM(179)3R | Project: 26296(05) | Category: 0300/TRAFFIC NH-STIM(179)3R | ||||||||
0015 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 854(A) 8800 | LF | 21,000.000 | 21,000.000 | 28,510.000 | $0.07 | $0.00 | $1,995.70 | |
0016 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 854(C) 8530 | LF | 50,000.000 | 50,000.000 | 49,365.000 | 49,365.000 | $0.43 | $21,226.95 | $21,226.95 |
0017 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | 854(C) 8535 | LF | 22,000.000 | 22,000.000 | 15,888.000 | 15,888.000 | $0.44 | $6,990.72 | $6,990.72 |
0018 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 21,000.000 | 21,000.000 | 19,743.400 | $0.12 | $0.00 | $2,369.21 | |
0019 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.660 | $14,000.00 | $0.00 | $9,240.00 | |
Subtotals For Category 0300/TRAFFIC NH-STIM(179)3R | $28,217.67 | $41,822.58 | ||||||||
Subtotals For Project NH-STIM(179)3R /26296(05) | $28,217.67 | $2,194,821.11 |
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: NH-STIM(150)3R | Project: 26344(04) | Category: 0100/ROADWAY NH-STIM(150)3R | ||||||||
0020 | (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 411(S4) 5960 | TON | 2,000.000 | 2,000.000 | 2,162.970 | $79.90 | $0.00 | $172,821.30 | |
0021 | P.C. CONCRETE FOR PAVEMENT | 414(I) 5275 | CY | 9,900.000 | 9,900.000 | 9,769.160 | $86.00 | $0.00 | $840,147.76 | |
0022 | P.C. CONCRETE PAVEMENT(PLACEMENT ONLY) | 414(J) 5400 | SY | 65,700.000 | 65,700.000 | 66,329.290 | $5.30 | $0.00 | $351,545.24 | |
0023 | (SP)BONDED P.C.C. OVERLAY(PLACEMENT) | 414(K) 5550 | SY | 1,000.000 | 1,000.000 | 1,459.020 | $10.50 | $0.00 | $15,319.71 | |
0024 | COLD MILLING PAVEMENT | 417 5267 | SY | 66,000.000 | 66,000.000 | 8,394.580 | 76,180.180 | $0.75 | $6,295.94 | $57,135.14 |
Subtotals For Category 0100/ROADWAY NH-STIM(150)3R | $6,295.94 | $1,436,969.15 | ||||||||
Fed/State Project Number: NH-STIM(150)3R | Project: 26344(04) | Category: 0300/TRAFFIC NH-STIM(150)3R | ||||||||
0025 | TRAFFIC STRIPE(PAINT)(4" WIDE) | 854(A) 8800 | LF | 19,700.000 | 19,700.000 | 20,539.500 | $0.07 | $0.00 | $1,437.77 | |
0026 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 854(C) 8530 | LF | 40,000.000 | 40,000.000 | 42,229.500 | $0.40 | $0.00 | $16,891.80 | |
0027 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | 854(C) 8535 | LF | 14,400.000 | 14,400.000 | 457.000 | 5,941.000 | $0.41 | $187.37 | $2,435.81 |
0028 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 19,700.000 | 19,700.000 | 19,848.500 | $0.12 | $0.00 | $2,381.82 | |
0029 | CONSTRUCTION TRAFFIC CONTROL | 880(J) 8905 | LSUM | 1.000 | 1.000 | 0.660 | $11,000.00 | $0.00 | $7,260.00 | |
Subtotals For Category 0300/TRAFFIC NH-STIM(150)3R | $187.37 | $30,407.20 | ||||||||
Subtotals For Project NH-STIM(150)3R /26344(04) | $6,483.31 | $1,467,376.35 |