Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    05/05/2010
Contract ID: 090279   Estimate Number: 0018     Contract No: 411139
Residency: ARDMORE (07200)   Estimate Type: Progressive     Account No: 400700

Project Number(s): STP-STIM(038), STP-STIM(040)
Primary Job Piece No: 09247(14)
Contract Description: BRIDGE, GRADE, DRAIN, SURFACE AND BRIDGE US 70: BEGIN AT JEFFERSON C/L, EXTEND EAST. OVER RED OAK CREEK 1.8 MILES EAST OF JEFFERSON C/L. PROJECT LENGTH = 3.367 MILES
Primary County: CARTER              
Name of Road: US-70              
Prime Contractor: SILVER STAR CONSTRUCTION COMPANY, INC.              
    2401 S. BROADWAY              
    MOORE , OK   73160              
Surety Company: AMERICAN STATES INSURANCE CO.              

Date Let: 03/19/2009 NTP Effective Date: 04/27/2009 Pay Period: 04/16/2010  TO  04/30/2010
Date Awarded: 03/30/2009 Date Work Began: 04/27/2009 Original Contract Time: 240
Date Contract Executed: 04/15/2009 Date Time Stopped: Current Time Charged: 369.00
Date NTP Issued: 04/16/2009 Completion Date: Current Time Allowed: 364.00
General Liability Expires: 05/19/2010 Workman's Comp Expires: 05/19/2010 Percent Time Used: 101.37 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $7,352,000.00 Total to Date Prev to Date This Estimate
Bid Amount: $7,352,000.00 Participating: $6,055,467.52 $5,789,055.43 $266,412.09
Percent Complete: 83.05 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $1,245,875.97 Non ARRA: $0.00 $0.00 $0.00
Unearned Balance: $1,245,875.97 Total Earnings: $6,055,467.52 $5,789,055.43 $266,412.09
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $6,055,467.52 $5,789,055.43 $266,412.09
Other Adjustments: $60,656.51 $31,084.92 $29,571.59
Liq Dam/Disincentive: $-10,000.00 $0.00 $-10,000.00
TOTAL: $6,106,124.03 $5,820,140.35 $285,983.68

Estimate Adjustment Detail

Contract ID: 090279   Estimate Number: 0018     Primary JP: 09247(14)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Revised SP 108-STIM01 Approved 05/05/2009 0.0 $0.00
002 Revised Profile Grades Pending 0 0.0 $0.00
003 Time Suspension Approved 04/01/2010 3.0 $0.00


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
09247(14) 0033 RSTL EPXY FABS (AML) Stockpiled Material Adjustment 0010 $-7,140.21
09247(14) 0033 RSTL EPXY FABS (AML) Stockpiled Material Initial Payment 0008 $7,140.21
09247(14) 0034 RSTL EPXY FABS (AML) Stockpiled Material Initial Payment 0008 $2,981.53
09247(14) 0034 RSTL EPXY FABS (AML) Stockpiled Material Adjustment 0011 $-2,981.53
09247(14) 0040 RSTL EPXY FABS (AML) Stockpiled Material Initial Payment 0008 $20,182.05
09247(14) 0040 RSTL EPXY FABS (AML) Stockpiled Material Adjustment 0008 $-20,182.05
09247(14) 0041 PILES, FURNISHED (HP10X42) Stockpiled Material Initial Payment 0001 $12,422.50
09247(14) 0041 PILES, FURNISHED (HP10X42) Stockpiled Material Adjustment 0008 $-12,422.50
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0018 -5.0 $2,000.00 $-10,000.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
09247(14) 0015 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0013 0.00 $0.00 $170.22
09247(14) 0015 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0014 0.00 $0.00 $-3,773.22
09247(14) 0015 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $3,773.22
09247(14) 0015 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $-838.94
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0007 0.00 $0.00 $191.10
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0008 0.00 $0.00 $245.00
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0009 0.00 $0.00 $15.40
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0011 0.00 $0.00 $269.96
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0014 0.00 $0.00 $47.56
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * QAQC 0015 0.00 $0.00 $20.69
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0016 0.00 $0.00 $62.71
09247(14) 0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0018 0.00 $0.00 $129.31
09247(14) 0017 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0017 0.00 $0.00 $2,798.26
09247(14) 0018 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0017 0.00 $0.00 $1,439.48
09247(14) 0018 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $-116.70
09247(14) 0034 CONCRETE RAIL (TR4) * Material Discrepancy Adjustments 0011 0.00 $0.00 $-4,641.86
09247(14) 0036 CLASS AA CONCRETE * Material Discrepancy Adjustments 0011 0.00 $0.00 $-3,360.47
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0013 0.00 $0.00 $918.42
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0014 0.00 $0.00 $-19,369.24
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0014 0.00 $0.00 $1,246.58
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0015 0.00 $0.00 $810.38
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * QAQC 0015 0.00 $0.00 $1,420.75
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $-4,306.58
09247(15) 0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $19,369.24
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0007 0.00 $0.00 $123.31
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0008 0.00 $0.00 $2,039.17
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0009 0.00 $0.00 $1,161.15
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0010 0.00 $0.00 $440.52
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0011 0.00 $0.00 $2,275.38
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0012 0.00 $0.00 $883.16
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0013 0.00 $0.00 $1,792.05
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0014 0.00 $0.00 $2,127.56
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) * QAQC 0015 0.00 $0.00 $1,199.05
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0015 0.00 $0.00 $1,246.47
09247(15) 0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) Asphalt Binder Adjustment 0016 0.00 $0.00 $1,784.00
09247(15) 0081 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0017 0.00 $0.00 $17,380.65
09247(15) 0081 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0018 0.00 $0.00 $10,597.05
09247(15) 0082 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0011 0.00 $0.00 $230.63
09247(15) 0082 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0017 0.00 $0.00 $19,890.10
09247(15) 0082 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0018 0.00 $0.00 $2,068.89
09247(15) 0082 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0018 0.00 $0.00 $-1,103.90
Subtotals For Line Item Adjustments $60,656.51
* = User applied Line Item Adjustments


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090279   Estimate Number: 0018     Primary JP: 09247(14)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(038) Project:    09247(14) Category:    0100/ROADWAY STP-STIM(038)
0001 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000   1.000 $15,200.00 $0.00 $15,200.00
0002 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 11,765.000 11,765.000   10,584.000 $2.40 $0.00 $25,401.60
0003 UNCLASSIFIED BORROW 202(C) 0184 CY 22,161.000 22,161.000   0.000 $1.00 $0.00 $0.00
0004 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   0.500 $19,775.00 $0.00 $9,887.50
0005 TEMPORARY SILT DIKE 227 0100 LF 84.000 84.000   42.000 $8.30 $0.00 $348.60
0006 SOLID SLAB SODDING 230(A) 2806 SY 13,109.000 13,109.000   5,736.000 $1.45 $0.00 $8,317.20
0007 MULCH SODDING 230(B) 2807 SY 20,492.000 20,492.000   0.000 $1.45 $0.00 $0.00
0008 SEEDING METHOD B 232(B) 2814 AC 7.000 7.000   0.000 $415.00 $0.00 $0.00
0009 VEGETATIVE MULCHING 233(A) 2817 AC 7.000 7.000 0.960 0.960 $415.00 $398.40 $398.40
0010 MOWING 241 2832 AC 14.000 14.000   3.060 $57.00 $0.00 $174.42
0011 (SP)STABILIZED SUBGRADE 327(K) 4300 SY 7,533.000 7,533.000   6,430.000 $3.50 $0.00 $22,505.00
0012 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 9.000 9.000   0.000 $40.00 $0.00 $0.00
0013 TACK COAT 407 0250 GAL 1,043.000 1,043.000 25.000 702.500 $3.00 $75.00 $2,107.50
0014 PRIME COAT 408 5774 GAL 1,164.000 1,164.000   535.300 $3.00 $0.00 $1,605.90
0015 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) 411(S3) 5935 TON 672.000 672.000 0.000 618.760 $65.50 $0.00 $40,528.78
0016 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 3,567.000 3,567.000 27.600 2,792.500 $53.80 $1,484.88 $150,236.51
0017 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 448.000 448.000 0.000 522.610 $71.70 $0.00 $37,471.14
0018 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 466.000 466.000 0.000 268.840 $72.35 $0.00 $19,450.57
0019 CLASS C CONCRETE 509(D) 0325 CY 198.000 198.000   183.150 $228.00 $0.00 $41,758.20
0020 TYPE B4 CULVERT END TREATMENT 613(CC) 7187 EA 1.000 1.000   0.000 $940.00 $0.00 $0.00
0021 TYPE B6 CULVERT END TREATMENT 613(CC) 7197 EA 1.000 1.000   0.000 $1,420.00 $0.00 $0.00
0022 24" CORR. GALV. STEEL PIPE 613(D) 0690 LF 102.000 102.000   0.000 $37.30 $0.00 $0.00
0023 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 4,192.000 4,192.000 4,666.670 4,666.670 $1.60 $7,466.67 $7,466.67
0024 REMOVAL OF GUARD RAIL 619(B) 4780 LF 651.000 651.000 664.000 664.000 $3.10 $2,058.40 $2,058.40
0025 SAWING PAVEMENT 619(C) 0924 LF 80.000 80.000   0.000 $4.15 $0.00 $0.00
0026 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 700.000 700.000   700.000 $16.10 $0.00 $11,270.00
0027 BEAM GUARD RAIL-THRIE-BEAM TRANSITION SECTION 623(E) 7113 EA 4.000 4.000   4.000 $1,505.00 $0.00 $6,020.00
0028 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 4.000 4.000   4.000 $2,180.00 $0.00 $8,720.00
0029 (SP)FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 1,394.000 1,394.000   1,500.000 $3.20 $0.00 $4,800.00
Subtotals For Category     0100/ROADWAY STP-STIM(038)    $11,483.35 $415,726.39
Fed/State Project Number:    STP-STIM(038) Project:    09247(14) Category:    0200/BRIDGE 'B' STP-STIM(038)
0030 SUBSTRUCTURE EXCAVATION COMMON 501(B) 1307 CY 90.000 90.000   90.000 $23.25 $0.00 $2,092.50
0031 CLSM BACKFILL 501(G) 6309 CY 136.000 136.000   136.000 $151.00 $0.00 $20,536.00
0032 PRESTRESSED CONCRETE BEAMS (TYPE III) 503(A) 1312 LF 657.000 657.000   657.000 $203.00 $0.00 $133,371.00
0033 APPROACH SLAB 504(A) 1304 SY 224.800 224.800   224.800 $145.50 $0.00 $32,708.40
0034 CONCRETE RAIL (TR4) 504(E) 6245 LF 427.000 427.000   427.000 $67.50 $0.00 $28,822.50
0035 STRUCTURAL STEEL 506(A) 1322 LB 1,050.000 1,050.000   1,050.000 $4.15 $0.00 $4,357.50
0036 CLASS AA CONCRETE 509(A) 1326 CY 228.700 228.700   228.700 $529.00 $0.00 $120,982.30
0037 CLASS A CONCRETE 509(B) 1328 CY 114.200 114.200   114.200 $519.00 $0.00 $59,269.80
0038 CLASS C CONCRETE 509(D) 1331 CY 25.000 25.000 7.870 7.870 $374.00 $2,943.38 $2,943.38
0039 REINFORCING STEEL 511(A) 1332 LB 560.000 560.000   560.000 $1.70 $0.00 $952.00
0040 EPOXY COATED REINFORCING STEEL 511(B) 6010 LB 71,290.000 71,290.000   71,290.000 $1.15 $0.00 $81,983.50
0041 PILES, FURNISHED (HP 10X42) 514(A) 6010 LF 623.000 623.000   623.000 $42.45 $0.00 $26,446.35
0042 PILES, DRIVEN (HP 10X42) 514(B) 6292 LF 623.000 623.000   619.780 $12.45 $0.00 $7,716.26
0043 PILE LOAD TEST (DYNAMIC) 514(F) 6354 EA 14.000 14.000   14.000 $640.00 $0.00 $8,960.00
0044 WATER REPELLENT (VISUALLY INSPECTED) 515(A) 6013 SY 745.000 745.000   745.000 $3.50 $0.00 $2,607.50
0045 DRILLED SHAFTS 48" DIAMETER 516(A) 6094 LF 234.000 234.000   238.930 $650.00 $0.00 $155,304.50
0046 (SP) SEALER CRACK PREPARATION 523(A) 6550 LF 163.000 163.000   162.000 $4.90 $0.00 $793.80
0047 (SP) SEALER RESIN 523(B) 6560 GAL 1.800 1.800   2.000 $228.00 $0.00 $456.00
0048 (PL)FIXED BEARING ASSEMBLY 535 6164 EA 8.000 8.000   8.000 $291.00 $0.00 $2,328.00
0049 (PL)EXPANSION BEARING ASSEMBLY 535 6165 EA 16.000 16.000   16.000 $970.00 $0.00 $15,520.00
0050 (PL)ELASTOMERIC BEARING PADS 535 6282 EA 16.000 16.000   16.000 $332.00 $0.00 $5,312.00
0051 TYPE I-A PLAIN RIPRAP 601(A-1)1353 TON 1,910.000 1,910.000   1,019.530 $41.50 $0.00 $42,310.50
0052 TYPE I-A FILTER BLANKET 601(A-2)1355 TON 360.000 360.000   172.670 $36.30 $0.00 $6,267.92
0053 6" PERFORATED PIPE UNDERDRAIN ROUND 613(P) 6204 LF 84.000 84.000   84.000 $25.60 $0.00 $2,150.40
0054 6" NON-PERF.PIPE UNDERDRAIN RND. 613(Q) 6207 LF 50.000 50.000   50.000 $25.60 $0.00 $1,280.00
0055 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   0.000 $31,135.00 $0.00 $0.00
Subtotals For Category     0200/BRIDGE 'B' STP-STIM(038)    $2,943.38 $765,472.11
Fed/State Project Number:    STP-STIM(038) Project:    09247(14) Category:    0300/TRAFFIC STP-STIM(038)
0056 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 6,000.000 6,000.000   0.000 $0.15 $0.00 $0.00
0057 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 1,500.000 1,500.000   0.000 $0.55 $0.00 $0.00
0058 BARRICADES(TYPE III) 880(C) 8842 SD 840.000 840.000   984.000 $0.10 $0.00 $98.40
0059 VERTICAL PANELS 880(D) 8854 SD 6,300.000 6,300.000   3,171.000 $0.10 $0.00 $317.10
0060 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 1,680.000 1,680.000   1,968.000 $0.01 $0.00 $19.68
0061 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 12,600.000 12,600.000   3,171.000 $0.01 $0.00 $31.71
0062 DRUMS 880(F) 8878 SD 6,300.000 6,300.000   0.000 $0.11 $0.00 $0.00
Subtotals For Category     0300/TRAFFIC STP-STIM(038)    $0.00 $466.89
Subtotals For Project STP-STIM(038) /09247(14) $14,426.73 $1,181,665.39


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0100/ROADWAY STP-STIM(040)
0063 CLEARING AND GRUBBING 201 0102 LSUM 1.000 1.000 0.250 1.000 $83,610.00 $20,902.50 $83,610.00
0064 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 205,972.000 205,972.000   113,079.000 $2.10 $0.00 $237,465.90
0065 UNCLASSIFIED BORROW 202(C) 0184 CY 3,522.000 3,522.000   0.000 $1.00 $0.00 $0.00
0066 TYPE A-SALVAGED TOPSOIL 205 4229 LSUM 1.000 1.000   0.350 $125,625.00 $0.00 $43,968.75
0067 TEMPORARY SILT FENCE 223 2801 LF 384.000 384.000   1,245.000 $6.00 $0.00 $7,470.00
0068 TEMPORARY SEDIMENT FILTER 224 2803 EA 1.000 1.000   0.000 $350.00 $0.00 $0.00
0069 TEMPORARY SILT DIKE 227 0100 LF 1,484.000 1,484.000   511.000 $9.50 $0.00 $4,854.50
0070 SOLID SLAB SODDING 230(A) 2806 SY 120,775.000 120,775.000 8,724.000 69,792.000 $1.45 $12,649.80 $101,198.40
0071 MULCH SODDING 230(B) 2807 SY 200,906.000 200,906.000   0.000 $1.45 $0.00 $0.00
0072 SEEDING METHOD B 232(B) 2814 AC 67.000 67.000   0.000 $415.00 $0.00 $0.00
0073 VEGETATIVE MULCHING 233(A) 2817 AC 67.000 67.000 16.550 22.940 $415.00 $6,868.25 $9,520.10
0074 MOWING 241 2832 AC 134.000 134.000   6.820 $57.00 $0.00 $388.74
0075 (SP)STABILIZED SUBGRADE 327(K) 4300 SY 81,962.000 81,962.000   80,213.610 $3.15 $0.00 $252,672.87
0076 TRAFFIC BOUND SURFACE COURSE TYPE E 403(E) 0225 TON 557.000 557.000 145.700 588.070 $22.00 $3,205.40 $12,937.54
0077 TACK COAT 407 0250 GAL 12,035.000 12,035.000 1,100.000 12,147.500 $3.00 $3,300.00 $36,442.50
0078 PRIME COAT 408 5774 GAL 14,041.000 14,041.000   5,007.780 $3.00 $0.00 $15,023.34
0079 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) 411(S3) 5935 TON 7,317.000 7,317.000 0.000 7,229.650 $61.53 $0.00 $444,840.37
0080 (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) 411(S3) 5945 TON 39,873.000 39,873.000 0.000 38,707.290 $51.00 $0.00 $1,974,071.79
0081 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 4,877.000 4,877.000 1,979.130 5,225.180 $67.00 $132,601.71 $350,087.06
0082 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 3,985.000 3,985.000 386.390 4,834.680 $53.40 $20,633.23 $258,171.92
0083 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 0313 CY 125.000 125.000   407.120 $15.50 $0.00 $6,310.37
0084 CLASS A CONCRETE 509(B) 0321 CY 449.000 449.000   459.530 $471.00 $0.00 $216,438.63
0085 CLASS C CONCRETE 509(D) 0325 CY 395.000 395.000 0.000 159.320 $228.00 $0.00 $36,324.96
0086 REINFORCING STEEL 511(A) 0332 LB 69,385.000 69,385.000   68,353.790 $0.67 $0.00 $45,797.04
0087 TYPE I PLAIN RIPRAP 601(A) 0297 TON 678.000 678.000   500.540 $32.00 $0.00 $16,017.28
0088 INLET (SMD-TYPE 2) 611(E) 6002 EA 1.000 1.000   0.000 $3,730.00 $0.00 $0.00
0089 18" R.C.PIPE CLASS III 613(B) 0491 LF 57.000 57.000   0.000 $47.95 $0.00 $0.00
0090 36" X 22" R.C.PIPE ARCH CLASS A-III 613(B) 4497 LF 67.000 67.000   72.000 $133.15 $0.00 $9,586.80
0091 51" X 31" R.C.PIPE ARCH CLASS A-III 613(B) 4499 LF 67.000 67.000   144.000 $170.45 $0.00 $24,544.80
0092 TYPE A4 CULVERT END TREATMENT 613(CC) 7186 EA 12.000 12.000   4.000 $799.00 $0.00 $3,196.00
0093 TYPE B4 CULVERT END TREATMENT 613(CC) 7187 EA 8.000 8.000   4.000 $965.00 $0.00 $3,860.00
0094 TYPE C4 CULVERT END TREATMENT 613(CC) 7188 EA 2.000 2.000   2.000 $1,690.00 $0.00 $3,380.00
0095 TYPE CC4 CULVERT END TREATMENT 613(CC) 7193 EA 1.000 1.000   1.000 $2,790.00 $0.00 $2,790.00
0096 TYPE A6 CULVERT END TREATMENT 613(CC) 7196 EA 12.000 12.000   4.000 $975.00 $0.00 $3,900.00
0097 TYPE B6 CULVERT END TREATMENT 613(CC) 7197 EA 8.000 8.000   3.000 $1,255.00 $0.00 $3,765.00
0098 TYPE C6 CULVERT END TREATMENT 613(CC) 7198 EA 2.000 2.000   2.000 $2,365.00 $0.00 $4,730.00
0099 TYPE CC6 CULVERT END TREATMENT 613(CC) 7203 EA 1.000 1.000   1.000 $3,928.00 $0.00 $3,928.00
0100 18" CORR. GALV. STEEL PIPE 613(D) 0689 LF 1,239.000 1,239.000   681.000 $32.00 $0.00 $21,792.00
0101 24" CORR. GALV. STEEL PIPE 613(D) 0690 LF 572.000 572.000   396.940 $37.30 $0.00 $14,805.86
0102 36" CORR. GALV. STEEL PIPE 613(D) 0692 LF 16.000 16.000   0.000 $48.00 $0.00 $0.00
0103 42" X 29" CORR. GALV. STEEL PIPE ARCH 613(D) 4530 LF 72.000 72.000   67.700 $53.30 $0.00 $3,608.41
0104 49" X 33" CORR. GALV. STEEL PIPE ARCH 613(D) 4531 LF 68.000 68.000   70.000 $63.90 $0.00 $4,473.00
0105 REMOVAL OF STRUCTURES & OBSTRUCTIONS 619(A) 0920 LSUM 1.000 1.000   0.250 $56,865.00 $0.00 $14,216.25
0106 REMOVAL OF ASPHALT PAVEMENT 619(B) 4728 SY 58,812.000 58,812.000 3,893.890 20,643.220 $1.40 $5,451.45 $28,900.51
0107 REMOVAL OF GUARD RAIL 619(B) 4780 LF 348.000 348.000 652.000 652.000 $3.10 $2,021.20 $2,021.20
0108 SAWING PAVEMENT 619(C) 0924 LF 6,064.000 6,064.000 1,655.000 1,880.000 $4.15 $6,868.25 $7,802.00
0109 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 650.000 650.000   0.000 $16.00 $0.00 $0.00
0110 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 2.000 2.000   0.000 $2,200.00 $0.00 $0.00
0111 FENCE-STYLE WWF 624(A) 4281 LF 1,600.000 1,600.000   1,588.000 $3.80 $0.00 $6,034.40
0112 GATES-STYLE WWF (4.5'HIGH X 16'LONG) 624(B) 4466 EA 1.000 1.000   1.000 $520.00 $0.00 $520.00
0113 (SP)FENCE-STYLE SWF (5 BARBED WIRE) 624(C) 4459 LF 14,412.000 14,412.000   13,750.000 $3.70 $0.00 $50,875.00
0114 MAILBOX INSTALLATION-SINGLE 629(A) 4958 EA 6.000 6.000   0.000 $65.00 $0.00 $0.00
0115 MAILBOX 629(C) 4960 EA 8.000 8.000   0.000 $27.00 $0.00 $0.00
0116 REMOVAL OF MAILBOX INSTALLATION 629(D) 4961 EA 6.000 6.000   0.000 $11.00 $0.00 $0.00
Subtotals For Category     0100/ROADWAY STP-STIM(040)    $214,501.79 $4,372,341.29
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0200/BRIDGE 'A' STP-STIM(040)
0117 UNCLASSIFIED EXCAVATION 202(A) 1301 CY 1,215.000 1,215.000   555.700 $6.20 $0.00 $3,445.34
0118 STRUCTURAL EXCAVATION UNCLASSIFIED 501(A) 1306 CY 270.000 270.000   270.000 $15.50 $0.00 $4,185.00
0119 CLASS AA CONCRETE 509(A) 1326 CY 491.900 491.900   391.000 $378.80 $0.00 $148,110.80
0120 REINFORCING STEEL 511(A) 1332 LB 75,400.000 75,400.000   65,000.000 $0.67 $0.00 $43,550.00
0121 TYPE II SPECIAL PLAIN RIPRAP 601(B) 1357 TON 420.000 420.000   173.360 $33.00 $0.00 $5,720.88
0122 REMOVAL OF EXISTING BRIDGE STRUCTURE 619(D) 1397 LSUM 1.000 1.000   0.000 $1,868.00 $0.00 $0.00
Subtotals For Category     0200/BRIDGE 'A' STP-STIM(040)    $0.00 $205,012.02
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0300/TRAFFIC STP-STIM(040)
0123 CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) 856(A) 8839 LF 65,000.000 65,000.000   31,185.000 $0.13 $0.00 $4,054.05
0124 PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) 859(A) 8006 LF 6,000.000 6,000.000   1,230.000 $0.53 $0.00 $651.90
0125 CONSTRUCTION SIGNS 0 TO 6.25 SF 880(B) 8818 SD 5,250.000 5,250.000 -3,990.000 5,785.000 $0.53 $-2,114.70 $3,066.05
0126 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF 880(B) 8821 SD 3,150.000 3,150.000 380.000 2,793.000 $0.53 $201.40 $1,480.29
0127 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF 880(B) 8824 SD 3,150.000 3,150.000 210.000 3,610.000 $3.20 $672.00 $11,552.00
0128 BARRICADES(TYPE III) 880(C) 8842 SD 9,660.000 9,660.000 280.000 3,315.000 $0.11 $30.80 $364.65
0129 WING BARRICADES 880(C) 8848 SD 420.000 420.000 10.000 747.000 $0.27 $2.70 $201.69
0130 VERTICAL PANELS 880(D) 8854 SD 68,250.000 68,250.000 702.000 37,942.000 $0.11 $77.22 $4,173.62
0131 WARNING LIGHTS(TYPE A) 880(E) 8860 SD 21,000.000 21,000.000 740.000 10,486.000 $0.01 $7.40 $104.86
0132 WARNING LIGHTS(TYPE C) 880(E) 8872 SD 106,050.000 106,050.000 2,550.000 49,144.000 $0.01 $25.50 $491.44
0133 DRUMS 880(F) 8878 SD 34,700.000 34,700.000 2,480.000 17,201.000 $0.11 $272.80 $1,892.11
Subtotals For Category     0300/TRAFFIC STP-STIM(040)    $-824.88 $28,032.66
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0301/TRAFFIC SIGNING STP-STIM(040)
0134 SHEET ALUMINUM SIGNS 850(A) 8110 SF 142.580 142.580   0.000 $17.06 $0.00 $0.00
0135 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 274.000 274.000   0.000 $12.80 $0.00 $0.00
0136 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 55,530.000 55,530.000 60,985.000 60,985.000 $0.52 $31,712.20 $31,712.20
0137 TRAFFIC STRIPE(PLASTIC)(24" WIDE) 855(A) 8825 LF 88.000 88.000   0.000 $6.40 $0.00 $0.00
Subtotals For Category     0301/TRAFFIC SIGNING STP-STIM(040)    $31,712.20 $31,712.20
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0600/STAKING STP-STIM(040)
0138 STAKING 642 0098 LSUM 1.000 1.000   0.750 $52,560.00 $0.00 $39,420.00
Subtotals For Category     0600/STAKING STP-STIM(040)    $0.00 $39,420.00
Fed/State Project Number:    STP-STIM(040) Project:    09247(15) Category:    0640/CONSTRUCTION STP-STIM(040)
0139 (SP)SWPPP DOCUMENTATION AND MANAGEMENT 220 2800 LSUM 1.000 1.000   0.750 $7,520.00 $0.00 $5,640.00
0140 FIELD OFFICE 640 1426 EA 1.000 1.000   0.000 $19,680.00 $0.00 $0.00
0141 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $165,258.96 $0.00 $165,258.96
0142 (SP)CONTRACTORS QUALITY CONTROL 643 0087 LSUM 1.000 1.000 0.250 1.000 $26,385.00 $6,596.25 $26,385.00
Subtotals For Category     0640/CONSTRUCTION STP-STIM(040)    $6,596.25 $197,283.96
Subtotals For Project STP-STIM(040) /09247(15) $251,985.36 $4,873,802.13