Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    12/17/2010
Contract ID: 090225   Estimate Number: 0012     Contract No: 411157
Residency: ARDMORE (07200)   Estimate Type: Progressive     Account No: 400700

Project Number(s): IM-STIM(120)3R
Primary Job Piece No: 26402(04)
Contract Description: RESURFACE (ASPHALT) I-35: BEGIN AT THE CARTER C/L, EXTEND NORTH. PROJECT LENGTH = 6.56 MILES.
Primary County: MURRAY              
Name of Road: I-35              
Prime Contractor: SILVER STAR CONSTRUCTION COMPANY, INC.              
    2401 S. BROADWAY              
    MOORE , OK   73160              
Surety Company: AMERICAN STATES INSURANCE CO.              

Date Let: 03/24/2009 NTP Effective Date: 04/27/2009 Pay Period: 04/01/2010  TO  09/30/2010
Date Awarded: 03/30/2009 Date Work Began: 05/26/2009 Original Contract Time: 85
Date Contract Executed: 04/15/2009 Date Time Stopped: Current Time Charged: 522.00
Date NTP Issued: 04/16/2009 Completion Date: Current Time Allowed: 506.00
General Liability Expires: 05/19/2011 Workman's Comp Expires: 05/19/2011 Percent Time Used: 103.16 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $5,409,844.91 Total to Date Prev to Date This Estimate
Bid Amount: $5,186,400.00 Participating: $5,357,235.84 $5,280,482.82 $76,753.02
Percent Complete: 99.15 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $46,006.53 Non ARRA: $19,574.58 $19,574.58 $0.00
Unearned Balance: $-177,438.38 Total Earnings: $5,376,810.42 $5,300,057.40 $76,753.02
Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $5,376,810.42 $5,300,057.40 $76,753.02
Other Adjustments: $3,027.96 $7,511.92 $-4,483.96
Liq Dam/Disincentive: $-16,000.00 $-16,000.00 $0.00
TOTAL: $5,363,838.38 $5,291,569.32 $72,269.06

Estimate Adjustment Detail

Contract ID: 090225   Estimate Number: 0012     Primary JP: 26402(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Revised Special Revsion 108-STIM01 Approved 05/05/2009 0.0 $0.00
002 Replace Transverse Tie Bars Approved 10/21/2009 2.0 $3,363.57
003 Mounting Bracket for Concrete Box Culvert Approved 02/11/2010 3.0 $16,211.01
004 Additional Appropriations for Aspahlt and Cold Milling Approved 02/02/2010 0.0 $130,531.99
006 Change #6 Smoothness Pay Adjustment Approved 10/05/2010 0.0 $73,338.34


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0007 -1.0 $1,000.00 $-1,000.00
System Application of Liquidated Damages 0008 -9.0 $1,000.00 $-9,000.00
System Application of Liquidated Damages 0009 -6.0 $1,000.00 $-6,000.00
System Application of Liquidated Damages 0010 -5.0 $1,000.00 $-5,000.00
System Application of Liquidated Damages 0011 --5.0 $1,000.00 $5,000.00
System Application of Liquidated Damages 0012 -0.0 $1,000.00 $0.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
26402(04) 0002 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) * Asphalt Binder Adjustment 0012 0.00 $0.00 $-16.57
26402(04) 0002 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) Asphalt Binder Adjustment 0012 4.51 $3.63 $16.39
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * ROADWAY DENSITY 0003 -6,670.70 $66.15 $-441,266.81
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0005 0.00 $0.00 $5,347.57
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * ROADWAY DENSITY 0005 6,670.70 $66.15 $441,266.81
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * ROADWAY DENSITY 0005 -2,817.85 $66.15 $-186,400.78
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * ROADWAY DENSITY 0008 2,817.85 $66.15 $186,400.78
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Material Discrepancy Adjustments 0012 0.00 $0.00 $-710.28
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Asphalt Binder Adjustment 0012 0.00 $0.00 $-34.17
26402(04) 0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0012 9.49 $4.15 $39.43
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0005 0.00 $0.00 $1,870.50
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0006 0.00 $0.00 $293.85
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0008 -3,903.94 $72.60 $-283,426.04
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0009 3,903.94 $72.60 $283,426.04
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0010 0.00 $0.00 $-71,817.84
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Material Discrepancy Adjustments 0011 989.22 $72.60 $71,817.84
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) Asphalt Binder Adjustment 0012 -24.02 $4.15 $-99.79
26402(04) 0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) * Asphalt Binder Adjustment 0012 0.00 $0.00 $86.47
26402(04) 0005 RUMBLE STRIP-METHOD AC-CON * SUBSTANDARD ITEM 0012 -496.00 $0.14 $-69.44
26402(04) 0017 (PL)TRUCK MOUNTED ATTENUATOR * SUBSTANDARD ITEM 0012 -112.00 $33.00 $-3,696.00
Subtotals For Line Item Adjustments $3,027.96
* = User applied Line Item Adjustments


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090225   Estimate Number: 0012     Primary JP: 26402(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    IM-STIM(120)3R Project:    26402(04) Category:    0100/ROADWAY
0001 (SP)ULTRATHIN BONDED WEARING COURSE 411 4280 SY 291,300.000 291,300.000 0.000 291,623.670 $4.75 $0.00 $1,385,212.44
0002 (SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) 411(S3) 5935 TON 1,152.000 1,728.720 4.510 1,733.230 $68.35 $308.26 $118,466.27
0003 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 33,510.000 33,510.000 9.490 33,479.350 $66.15 $627.76 $2,214,658.99
0004 (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) 411(S4) 5960 TON 3,255.000 3,903.940 -24.020 3,879.920 $72.60 $-1,743.85 $281,682.20
0005 RUMBLE STRIP-METHOD AC-CON 413(A) 4861 LF 106,762.000 106,762.000 280.000 106,861.000 $0.14 $39.20 $14,960.54
0006 H.E.S. CONCRETE (FULL DEPTH PATCHING) 414(B) 5913 SY 100.000 100.000   38.390 $325.00 $0.00 $12,476.75
0007 COLD MILLING BITUMINOUS PAVEMENT 417 4267 SY 265,900.000 301,100.110 -1.030 301,099.080 $1.25 $-1.29 $376,373.85
0008 CONCRETE PARAPET 504(F) 1381 LF 60.700 60.700   60.680 $652.50 $0.00 $39,593.70
0009 REMOVAL OF GUARD RAIL 619(B) 4780 LF 9,150.000 9,150.000   8,911.000 $1.60 $0.00 $14,257.60
0010 BEAM GUARD RAIL-W-BEAM-SINGLE 623(A) 0932 LF 8,000.000 8,000.000   8,000.000 $15.90 $0.00 $127,200.00
0011 THRIE BEAM BRIDGE CONNECTION-TYPE A 623(E) 7114 EA 8.000 8.000 1.000 8.000 $1,588.00 $1,588.00 $12,704.00
0012 GUARD RAIL ANCHOR UNIT (TYPE B) 623(F) 4447 EA 6.000 6.000   6.000 $529.15 $0.00 $3,174.90
0013 GUARD RAIL ANCHOR UNIT (TYPE GE) 623(F) 4453 EA 2.000 2.000   2.000 $635.00 $0.00 $1,270.00
0014 (SP)G.E.T. GUARD RAIL END SECTION 623(H) 8571 EA 16.000 16.000   16.000 $2,650.00 $0.00 $42,400.00
0015 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 155,830.000 155,830.000   175,701.000 $0.43 $0.00 $75,551.43
0016 TRAFFIC STRIPE(PLASTIC)(6" WIDE) 855(A) 8813 LF 22,836.000 22,836.000   24,072.000 $0.65 $0.00 $15,646.80
0017 (PL)TRUCK MOUNTED ATTENUATOR 876(C) 8482 SD 45.000 45.000 112.000 155.000 $33.00 $3,696.00 $5,115.00
0018 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000 0.300 1.000 $18,250.00 $5,475.00 $18,250.00
0019 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 45.000 45.000   169.000 $93.50 $0.00 $15,801.50
8003 PAVEMENT/BRIDGE SMOOTHNESS ADJUSTMENT 430 5010 LSUM 0.000 1.000 1.000 1.000 $73,338.34 $73,338.34 $73,338.34
Subtotals For Category     0100/ROADWAY    $83,327.42 $4,848,134.31
Fed/State Project Number:    IM-STIM(120)3R Project:    26402(04) Category:    0101/ROADWAY ADD ALT
0020 UNCLASSIFIED EXCAVATION 202(A) 0183 CY 2,434.000 2,434.000   1,393.290 $11.55 $0.00 $16,092.51
0021 AGGREGATE BASE 303 0192 CY 2,434.000 2,434.000 -192.040 1,201.250 $32.00 $-6,145.28 $38,440.00
0022 SEPARATOR FABRIC 325 5271 SY 4,520.000 4,520.000   4,190.040 $2.55 $0.00 $10,684.61
0023 8" P.C. CONCRETE PAVEMENT(CONT.REINF.) 414(D) 4366 SY 1,440.000 1,440.000   1,682.000 $73.90 $0.00 $124,299.80
0024 REMOVAL OF CONCRETE PAVEMENT 619(B) 4727 SY 1,440.000 1,440.000   1,744.470 $33.30 $0.00 $58,090.86
0025 RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN 627(O) 4410 LF 4,200.000 4,200.000   0.000 $4.05 $0.00 $0.00
0026 RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER 627(P) 4425 LF 4,200.000 4,200.000 -18.000 4,513.000 $23.84 $-429.12 $107,589.92
0027 EDGE DRAIN CONDUIT-PERFORATED 653(A) 5915 LF 1,150.000 1,150.000   1,047.000 $10.25 $0.00 $10,731.75
0028 EDGE DRAIN OUTLET LATERAL-NONPERFORATED 653(B) 5916 LF 240.000 240.000   229.000 $34.90 $0.00 $7,992.10
0029 OUTLET LATERAL HEADWALL 653(C) 5946 EA 12.000 12.000   12.000 $530.00 $0.00 $6,360.00
Subtotals For Category     0101/ROADWAY ADD ALT    $-6,574.40 $380,281.55
Fed/State Project Number:    IM-STIM(120)3R Project:    26402(04) Category:    0640/CONSTRUCTION
0030 MOBILIZATION 641 1399 LSUM 1.000 1.000   1.000 $128,819.97 $0.00 $128,819.98
Subtotals For Category     0640/CONSTRUCTION    $0.00 $128,819.98
Fed/State Project Number:    IM-STIM(120)3R Project:    26402(04) Category:    0850/Non ARRA Funding
8000 CONSTRUCTION MISCELLANEOUS 104 0600 EA 0.000 399.000   399.000 $8.43 $0.00 $3,363.57
8001 CONSTRUCTION MISCELLANEOUS 104 0600 EA 0.000 19.000   19.000 $819.31 $0.00 $15,566.89
8002 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 0.000 1.000   1.000 $644.12 $0.00 $644.12
Subtotals For Category     0850/Non ARRA Funding    $0.00 $19,574.58
Subtotals For Project IM-STIM(120)3R /26402(04) $76,753.02 $5,376,810.42