| Fed/State Project Number: IM-STIM(120)3R |
Project: 26402(04) |
Category: 0100/ROADWAY |
| 0001 |
(SP)ULTRATHIN BONDED WEARING COURSE |
411 4280 |
SY |
291,300.000 |
291,300.000 |
|
0.000 |
$4.75 |
$0.00 |
$0.00 |
| 0002 |
(SP)ASPHALT CONCRETE TYPE S3(PG 76-28 OK) |
411(S3) 5935 |
TON |
1,152.000 |
1,152.000 |
1,635.490 |
1,635.490 |
$68.35 |
$111,785.74 |
$111,785.74 |
| 0003 |
(SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) |
411(S4) 5950 |
TON |
33,510.000 |
33,510.000 |
2,445.220 |
2,445.220 |
$66.15 |
$161,751.30 |
$161,751.30 |
| 0004 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) |
411(S4) 5960 |
TON |
3,255.000 |
3,255.000 |
|
0.000 |
$72.60 |
$0.00 |
$0.00 |
| 0005 |
RUMBLE STRIP-METHOD AC-CON |
413(A) 4861 |
LF |
106,762.000 |
106,762.000 |
|
0.000 |
$0.14 |
$0.00 |
$0.00 |
| 0006 |
H.E.S. CONCRETE (FULL DEPTH PATCHING) |
414(B) 5913 |
SY |
100.000 |
100.000 |
|
0.000 |
$325.00 |
$0.00 |
$0.00 |
| 0007 |
COLD MILLING BITUMINOUS PAVEMENT |
417 4267 |
SY |
265,900.000 |
265,900.000 |
47,777.720 |
54,838.550 |
$1.25 |
$59,722.15 |
$68,548.19 |
| 0008 |
CONCRETE PARAPET |
504(F) 1381 |
LF |
60.700 |
60.700 |
|
0.000 |
$652.50 |
$0.00 |
$0.00 |
| 0009 |
REMOVAL OF GUARD RAIL |
619(B) 4780 |
LF |
9,150.000 |
9,150.000 |
|
0.000 |
$1.60 |
$0.00 |
$0.00 |
| 0010 |
BEAM GUARD RAIL-W-BEAM-SINGLE |
623(A) 0932 |
LF |
8,000.000 |
8,000.000 |
|
0.000 |
$15.90 |
$0.00 |
$0.00 |
| 0011 |
THRIE BEAM BRIDGE CONNECTION-TYPE A |
623(E) 7114 |
EA |
8.000 |
8.000 |
|
0.000 |
$1,588.00 |
$0.00 |
$0.00 |
| 0012 |
GUARD RAIL ANCHOR UNIT (TYPE B) |
623(F) 4447 |
EA |
6.000 |
6.000 |
|
0.000 |
$529.15 |
$0.00 |
$0.00 |
| 0013 |
GUARD RAIL ANCHOR UNIT (TYPE GE) |
623(F) 4453 |
EA |
2.000 |
2.000 |
|
0.000 |
$635.00 |
$0.00 |
$0.00 |
| 0014 |
(SP)G.E.T. GUARD RAIL END SECTION |
623(H) 8571 |
EA |
16.000 |
16.000 |
|
0.000 |
$2,650.00 |
$0.00 |
$0.00 |
| 0015 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) |
855(A) 8812 |
LF |
155,830.000 |
155,830.000 |
|
0.000 |
$0.43 |
$0.00 |
$0.00 |
| 0016 |
TRAFFIC STRIPE(PLASTIC)(6" WIDE) |
855(A) 8813 |
LF |
22,836.000 |
22,836.000 |
|
0.000 |
$0.65 |
$0.00 |
$0.00 |
| 0017 |
(PL)TRUCK MOUNTED ATTENUATOR |
876(C) 8482 |
SD |
45.000 |
45.000 |
15.000 |
33.000 |
$33.00 |
$495.00 |
$1,089.00 |
| 0018 |
CONSTRUCTION TRAFFIC CONTROL |
880(J) 8905 |
LSUM |
1.000 |
1.000 |
0.150 |
0.500 |
$18,250.00 |
$2,737.50 |
$9,125.00 |
| 0019 |
PORT.CHANGEABLE MESSAGE SIGN |
882(B) 8306 |
SD |
45.000 |
45.000 |
35.000 |
71.000 |
$93.50 |
$3,272.50 |
$6,638.50 |
| Subtotals For Category 0100/ROADWAY |
$339,764.19 |
$358,937.73 |
|
| Fed/State Project Number: IM-STIM(120)3R |
Project: 26402(04) |
Category: 0101/ROADWAY ADD ALT |
| 0020 |
UNCLASSIFIED EXCAVATION |
202(A) 0183 |
CY |
2,434.000 |
2,434.000 |
519.520 |
716.730 |
$11.55 |
$6,000.46 |
$8,278.24 |
| 0021 |
AGGREGATE BASE |
303 0192 |
CY |
2,434.000 |
2,434.000 |
519.520 |
716.730 |
$32.00 |
$16,624.64 |
$22,935.36 |
| 0022 |
SEPARATOR FABRIC |
325 5271 |
SY |
4,520.000 |
4,520.000 |
3,231.700 |
4,190.040 |
$2.55 |
$8,240.84 |
$10,684.61 |
| 0023 |
8" P.C. CONCRETE PAVEMENT(CONT.REINF.) |
414(D) 4366 |
SY |
1,440.000 |
1,440.000 |
1,682.000 |
1,682.000 |
$73.90 |
$124,299.80 |
$124,299.80 |
| 0024 |
REMOVAL OF CONCRETE PAVEMENT |
619(B) 4727 |
SY |
1,440.000 |
1,440.000 |
803.350 |
1,744.470 |
$33.30 |
$26,751.56 |
$58,090.86 |
| 0025 |
RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN |
627(O) 4410 |
LF |
4,200.000 |
4,200.000 |
|
0.000 |
$4.05 |
$0.00 |
$0.00 |
| 0026 |
RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER |
627(P) 4425 |
LF |
4,200.000 |
4,200.000 |
906.200 |
4,531.000 |
$23.84 |
$21,603.81 |
$108,019.04 |
| 0027 |
EDGE DRAIN CONDUIT-PERFORATED |
653(A) 5915 |
LF |
1,150.000 |
1,150.000 |
735.000 |
1,047.000 |
$10.25 |
$7,533.75 |
$10,731.75 |
| 0028 |
EDGE DRAIN OUTLET LATERAL-NONPERFORATED |
653(B) 5916 |
LF |
240.000 |
240.000 |
|
0.000 |
$34.90 |
$0.00 |
$0.00 |
| 0029 |
OUTLET LATERAL HEADWALL |
653(C) 5946 |
EA |
12.000 |
12.000 |
|
0.000 |
$530.00 |
$0.00 |
$0.00 |
| Subtotals For Category 0101/ROADWAY ADD ALT |
$211,054.86 |
$343,039.66 |
|