Contract ID: | 090182 | Estimate Number: | 0017 | Contract No: | 411317 | |||
Residency: | WEWOKA (03300) | Estimate Type: | Progressive | Account No: | 400300 | |||
Project Number(s): | IM-STIM(011) | ||||||||||||
Primary Job Piece No: | 13626(06) | ||||||||||||
Contract Description: | RECONSTRUCT (CONCRETE) - NO ADDED LANES I-40: FROM 4.0 MILES EAST OF SH-99, EXTEND EAST. PROJECT LENGTH = 2.473 | ||||||||||||
Primary County: | SEMINOLE | ||||||||||||
Name of Road: | I-40 | ||||||||||||
Prime Contractor: | KOSS CONSTRUCTION COMPANY & SUBSIDIARY | ||||||||||||
5830 SW DRURY LANE | |||||||||||||
TOPEKA , KS 66604 | |||||||||||||
Surety Company: | FEDERAL INSURANCE COMPANY | ||||||||||||
Date Let: | 05/14/2009 | NTP Effective Date: | 07/13/2009 | Pay Period: | 02/01/2010 TO 03/31/2010 |
Date Awarded: | 05/19/2009 | Date Work Began: | 07/07/2009 | Original Contract Time: | 200 |
Date Contract Executed: | 06/03/2009 | Date Time Stopped: | 01/27/2010 | Current Time Charged: | 205.00 |
Date NTP Issued: | 06/12/2009 | Completion Date: | 01/27/2010 | Current Time Allowed: | 248.00 |
General Liability Expires: | 02/01/2011 | Workman's Comp Expires: | 02/01/2011 | Percent Time Used: | 82.66 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $9,964,811.12 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $9,882,380.61 | Participating: | $9,302,387.05 | $9,300,187.30 | $2,199.75 | ||
Percent Complete: | 95.63 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $435,954.77 | Non ARRA: | $392,638.05 | $390,852.00 | $1,786.05 | ||
Unearned Balance: | $353,524.26 | Total Earnings: | $9,695,025.10 | $9,691,039.30 | $3,985.80 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $9,695,025.10 | $9,691,039.30 | $3,985.80 | ||||
Other Adjustments: | $-31,168.75 | $-31,168.75 | $0.00 | ||||
Liq Dam/Disincentive: | $-135,000.00 | $-135,000.00 | $0.00 | ||||
TOTAL: | $9,528,856.35 | $9,524,870.55 | $3,985.80 |
Contract ID: | 090182 | Estimate Number: | 0017 | Primary JP: | 13626(06) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | To change Uncl. Excavation to Plan Quantity. | Approved | 07/20/2009 | 0.0 | $0.00 |
002 | Adding Five(5) new items to the contract | Approved | 11/03/2009 | 0.0 | $74,121.75 |
003 | Increase the price for Bridge Parapet. | Approved | 11/03/2009 | 0.0 | $6,361.01 |
004 | Adding one (1) new item to the contract. | Approved | 03/02/2010 | 0.0 | $1,947.75 |
005 | Adding Days to B Time | Approved | 03/18/2010 | 3.0 | $0.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
13626(06) | 0034 | Stockpiled Material Closure | 0012 | $0.01 | |
13626(06) | 0034 | Beam Guard Rail-W-Beam-Single | Stockpiled Material Initial Payment | 0008 | $89,116.75 |
13626(06) | 0034 | Beam Guard Rail-W-Beam-Single | Stockpiled Material Adjustment | 0008 | $-16,702.91 |
13626(06) | 0034 | Beam Guard Rail-W-Beam-Single | Stockpiled Material Adjustment | 0009 | $-27,803.60 |
13626(06) | 0034 | Beam Guard Rail-W-Beam-Single | Stockpiled Material Adjustment | 0012 | $-44,610.25 |
13626(06) | 0035 | Thrie Beam Bridge Connection-Type A | Stockpiled Material Adjustment | 0009 | $-1,382.00 |
13626(06) | 0035 | Thrie Beam Bridge Connection-Type A | Stockpiled Material Adjustment | 0008 | $-1,382.00 |
13626(06) | 0035 | Thrie Beam Bridge Connection-Type A | Stockpiled Material Adjustment | 0012 | $-2,764.00 |
13626(06) | 0035 | Thrie Beam Bridge Connection-Type A | Stockpiled Material Initial Payment | 0008 | $5,528.00 | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-1,216.99 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-2,394.34 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-3,563.13 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-6,531.25 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-4,354.16 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-6,531.25 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0010 | 0.00 | $0.00 | $-1,979.17 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0014 | 0.00 | $0.00 | $-517.68 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0014 | 0.00 | $0.00 | $-1,979.17 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0014 | 0.00 | $0.00 | $-1,583.33 |
13626(06) | 0019 | (SP)P.C. CONCRETE FOR PAVEMENT | * QAQC | 0014 | 0.00 | $0.00 | $-518.28 | Subtotals For Line Item Adjustments | $-31,168.75 | * = User applied Line Item Adjustments |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
01 | TIME 'B' BID | 136.00 | 151.00 | $7,500.00 | $-135,000.00 |
Contract ID: | 090182 | Estimate Number: | 0017 | Primary JP: | 13626(06) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0100/ROADWAY - IM-STIM(011) | ||||||||
0001 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 40,024.000 | 40,024.000 | 40,024.000 | $4.40 | $0.00 | $176,105.60 | |
0002 | UNCLASSIFIED BORROW | 202(C) 0184 | CY | 15,531.000 | 15,531.000 | 15,531.000 | $4.40 | $0.00 | $68,336.40 | |
0003 | TEMPORARY SILT FENCE | 223 2801 | LF | 4,800.000 | 4,800.000 | 3,702.000 | $2.00 | $0.00 | $7,404.00 | |
0004 | TEMPORARY SEDIMENT FILTER | 224 2803 | EA | 5.000 | 5.000 | 0.000 | $115.00 | $0.00 | $0.00 | |
0005 | TEMPORARY SILT DIKE | 227 0100 | LF | 455.000 | 455.000 | 0.000 | $9.00 | $0.00 | $0.00 | |
0006 | SOLID SLAB SODDING | 230(A) 2806 | SY | 61,327.000 | 61,327.000 | 72,970.280 | $1.50 | $0.00 | $109,455.42 | |
0007 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 12.670 | 12.670 | 1.720 | $400.00 | $0.00 | $688.00 | |
0008 | MOWING | 241 2832 | AC | 12.670 | 12.670 | 0.000 | $49.00 | $0.00 | $0.00 | |
0009 | (SP)FLY ASH | 327(A) 4200 | TON | 6,440.000 | 644.000 | 0.000 | $45.00 | $0.00 | $0.00 | |
0010 | (SP)LIME | 327(D) 4230 | TON | 217.000 | 217.000 | 297.550 | $146.00 | $0.00 | $43,442.30 | |
0011 | (SP)CEMENTITIOUS STABILIZED SUBGRADE | 327(E) 4240 | SY | 133,487.000 | 133,487.000 | 146,864.550 | $2.65 | $0.00 | $389,191.07 | |
0012 | (SP)LIME PRETREATMENT | 327(G) 4260 | SY | 21,432.000 | 21,432.000 | 30,676.890 | $1.00 | $0.00 | $30,676.89 | |
0013 | TRAFFIC BOUND SURFACE COURSE TYPE E | 403(E) 0225 | TON | 1,517.000 | 1,517.000 | 1,498.710 | $28.00 | $0.00 | $41,963.88 | |
0014 | PRIME COAT | 408 5774 | GAL | 20,219.000 | 20,219.000 | 19,500.400 | $2.00 | $0.00 | $39,000.80 | |
0015 | (SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 411(S3) 5945 | TON | 22,697.000 | 22,697.000 | 21,479.870 | $61.60 | $0.00 | $1,323,159.99 | |
0016 | (SP)RUMBLE STRIP-METHOD PCC-CON | 413(D) 4868 | LF | 52,235.000 | 52,235.000 | 51,626.000 | $0.18 | $0.00 | $9,292.68 | |
0017 | (SP)P.C.CONCRETE PAVEMENT(PLACEMENT) | 414(A) 0210 | SY | 57,956.000 | 57,956.000 | 57,609.690 | $12.50 | $0.00 | $720,121.14 | |
0018 | (SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) | 414(A1) 5725 | SY | 76,264.000 | 76,264.000 | 75,009.990 | $13.75 | $0.00 | $1,031,387.37 | |
0019 | (SP)P.C. CONCRETE FOR PAVEMENT | 414(P) 6000 | CY | 43,522.000 | 43,522.000 | 43,224.860 | $78.00 | $0.00 | $3,371,539.08 | |
0020 | COLD MILLING PAVEMENT | 417 5267 | SY | 11,733.000 | 11,733.000 | 10,078.570 | $3.98 | $0.00 | $40,112.71 | |
0021 | INLET (SMD-TYPE 1) | 611(E) 6000 | EA | 4.000 | 4.000 | 0.000 | $2,765.00 | $0.00 | $0.00 | |
0022 | 24" R.C.PIPE CLASS III | 613(B) 0492 | LF | 500.000 | 500.000 | 0.000 | $51.00 | $0.00 | $0.00 | |
0023 | 36" R.C.PIPE CLASS III | 613(B) 0494 | LF | 100.000 | 100.000 | 0.000 | $80.00 | $0.00 | $0.00 | |
0024 | TYPE B6 CULVERT END TREATMENT | 613(CC) 7197 | EA | 2.000 | 2.000 | 0.000 | $1,500.00 | $0.00 | $0.00 | |
0025 | TYPE D6 CULVERT END TREATMENT | 613(CC) 7199 | EA | 4.000 | 4.000 | 0.000 | $2,300.00 | $0.00 | $0.00 | |
0026 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(P) 1091 | LF | 1,855.000 | 1,855.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0027 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(Q) 1096 | LF | 619.000 | 619.000 | 0.000 | $10.00 | $0.00 | $0.00 | |
0028 | PIPE UNDERDRAIN COVER MAT'L. | 613(R) 1100 | CY | 557.000 | 557.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0029 | REMOVAL OF HEADWALL | 619(B) 0291 | EA | 2.000 | 2.000 | 0.000 | $1,260.00 | $0.00 | $0.00 | |
0030 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 122,783.000 | 122,783.000 | 92,178.050 | $1.50 | $0.00 | $138,267.08 | |
0031 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 38,844.000 | 38,844.000 | 34,093.970 | $1.50 | $0.00 | $51,140.96 | |
0032 | REMOVAL OF GUARD RAIL | 619(B) 4780 | LF | 10,138.000 | 10,138.000 | 12,322.000 | $1.55 | $0.00 | $19,099.10 | |
0033 | SAWING PAVEMENT | 619(C) 0924 | LF | 20,094.000 | 20,094.000 | 1,714.000 | $0.01 | $0.00 | $17.14 | |
0034 | BEAM GUARD RAIL-W-BEAM-SINGLE | 623(A) 0932 | LF | 10,737.500 | 10,737.500 | 10,887.500 | $14.37 | $0.00 | $156,453.38 | |
0035 | THRIE BEAM BRIDGE CONNECTION-TYPE A | 623(E) 7114 | EA | 8.000 | 8.000 | 8.000 | $2,060.00 | $0.00 | $16,480.00 | |
0036 | GUARD RAIL ANCHOR UNIT (TYPE B) | 623(F) 4447 | EA | 24.000 | 24.000 | 20.000 | $721.00 | $0.00 | $14,420.00 | |
0037 | (SP)G.E.T. GUARD RAIL END SECTION | 623(H) 8571 | EA | 2.000 | 2.000 | 2.000 | $3,090.00 | $0.00 | $6,180.00 | |
Subtotals For Category 0100/ROADWAY - IM-STIM(011) | $0.00 | $7,803,934.99 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0200/BRIDGE "A" - IM-STIM(011) | ||||||||
0038 | COLD MILLING PAVEMENT | 417 5267 | SY | 429.000 | 429.000 | 432.780 | $18.45 | $0.00 | $7,984.79 | |
0039 | APPROACH SLAB | 504(A) 1304 | SY | 208.000 | 208.000 | 208.000 | $208.00 | $0.00 | $43,264.00 | |
0040 | CONCRETE PARAPET | 504(F) 1381 | LF | 295.800 | 0.000 | 0.000 | $55.89 | $0.00 | $0.00 | |
0041 | RAPID CURE JOINT SEALANT | 504(H) 6390 | LF | 78.800 | 78.800 | 76.000 | $38.55 | $0.00 | $2,929.80 | |
0042 | LATEX MODIFIED BRIDGE DECK OVERLAY | 505(D) 6087 | SY | 429.000 | 429.000 | 432.780 | $94.48 | $0.00 | $40,889.05 | |
0043 | HYDRODEMOLITION | 505(G) 1000 | SY | 429.000 | 429.000 | 432.780 | $68.87 | $0.00 | $29,805.56 | |
0044 | CLASS C CONCRETE | 509(D) 0325 | CY | 40.000 | 40.000 | 8.770 | $298.00 | $0.00 | $2,613.46 | |
0045 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 125.000 | 125.000 | 125.000 | $32.00 | $0.00 | $4,000.00 | |
Subtotals For Category 0200/BRIDGE "A" - IM-STIM(011) | $0.00 | $131,486.66 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0201/BRIDGE "B" - IM-STIM(011) | ||||||||
0046 | COLD MILLING PAVEMENT | 417 5267 | SY | 429.000 | 429.000 | 430.670 | $18.45 | $0.00 | $7,945.86 | |
0047 | APPROACH SLAB | 504(A) 1304 | SY | 179.400 | 179.400 | 179.400 | $208.00 | $0.00 | $37,315.20 | |
0048 | CONCRETE PARAPET | 504(F) 1381 | LF | 283.000 | 0.000 | 0.000 | $55.89 | $0.00 | $0.00 | |
0049 | RAPID CURE JOINT SEALANT | 504(H) 6390 | LF | 78.000 | 78.000 | 76.000 | $38.55 | $0.00 | $2,929.80 | |
0050 | LATEX MODIFIED BRIDGE DECK OVERLAY | 505(D) 6087 | SY | 429.000 | 429.000 | 430.660 | $94.48 | $0.00 | $40,688.76 | |
0051 | HYDRODEMOLITION | 505(G) 1000 | SY | 429.000 | 429.000 | 430.670 | $68.87 | $0.00 | $29,660.24 | |
0052 | CLASS C CONCRETE | 509(D) 0325 | CY | 40.000 | 40.000 | 8.730 | $298.00 | $0.00 | $2,601.54 | |
0053 | WATER REPELLENT (VISUALLY INSPECTED) | 515(A) 6013 | SY | 119.000 | 119.000 | 119.000 | $32.00 | $0.00 | $3,808.00 | |
Subtotals For Category 0201/BRIDGE "B" - IM-STIM(011) | $0.00 | $124,949.40 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0300/TRAFFIC SIGNING & STRIPING - IM-STIM(011) | ||||||||
0054 | RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN | 627(O) 4410 | LF | 17,200.000 | 17,200.000 | 17,098.000 | $2.50 | $0.00 | $42,745.00 | |
0055 | RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER | 627(P) 4425 | LF | 17,200.000 | 17,200.000 | 17,198.000 | $29.65 | $0.00 | $509,920.70 | |
0056 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 856(A) 8839 | LF | 54,000.000 | 54,000.000 | 181,159.000 | $0.20 | $0.00 | $36,231.80 | |
0057 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 | 856(G) 8887 | EA | 7,890.000 | 7,890.000 | 6,285.000 | 6,317.000 | $0.35 | $2,199.75 | $2,210.95 |
0058 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 34,500.000 | 34,500.000 | 128,121.000 | $0.10 | $0.00 | $12,812.10 | |
0059 | (PL)CONST.ZONE IMPACT ATTEN. | 871 8705 | SD | 900.000 | 900.000 | 0.000 | $1.00 | $0.00 | $0.00 | |
0060 | MODULAR GLARE SCREEN | 878(C) 8487 | SD | 17,100.000 | 17,100.000 | 13,444.000 | $0.30 | $0.00 | $4,033.20 | |
0061 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 300.000 | 300.000 | 306.000 | $22.00 | $0.00 | $6,732.00 | |
0062 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 3,000.000 | 3,000.000 | 3,756.000 | $0.90 | $0.00 | $3,380.40 | |
0063 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 8,000.000 | 8,000.000 | 9,290.000 | $1.25 | $0.00 | $11,612.50 | |
0064 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 9,500.000 | 9,500.000 | 4,775.000 | $0.35 | $0.00 | $1,671.25 | |
0065 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 5,500.000 | 5,500.000 | 3,060.000 | $0.15 | $0.00 | $459.00 | |
0066 | WING BARRICADES | 880(C) 8848 | SD | 600.000 | 600.000 | 824.000 | $5.00 | $0.00 | $4,120.00 | |
0067 | VERTICAL PANELS | 880(D) 8854 | SD | 41,500.000 | 41,500.000 | 23,699.000 | $0.28 | $0.00 | $6,635.72 | |
0068 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 17,000.000 | 17,000.000 | 9,450.000 | $0.03 | $0.00 | $283.50 | |
0069 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 58,500.000 | 58,500.000 | 15,497.000 | $0.04 | $0.00 | $619.88 | |
0070 | DRUMS | 880(F) 8878 | SD | 17,000.000 | 17,000.000 | 34,880.000 | $0.40 | $0.00 | $13,952.00 | |
0071 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 600.000 | 600.000 | 273.000 | $80.00 | $0.00 | $21,840.00 | |
0072 | PORT.CHANGEABLE MESSAGE SIGN | 882(B) 8306 | SD | 600.000 | 600.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
Subtotals For Category 0300/TRAFFIC SIGNING & STRIPING - IM-STIM(011) | $2,199.75 | $679,260.00 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0301/TRAFFIC - IM-STIM(011) | ||||||||
0073 | DELINEATORS(TYPE 1, CODE 1) | 853 9024 | EA | 46.000 | 46.000 | 43.000 | $15.00 | $0.00 | $645.00 | |
0074 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 854(C) 8530 | LF | 60,800.000 | 60,800.000 | 53,062.000 | $0.25 | $0.00 | $13,265.50 | |
0075 | (SP)TRAFFIC STRIPE(MULTI-POLYMER)(6" WIDE) | 854(C) 8535 | LF | 16,368.000 | 16,368.000 | 14,280.000 | $0.60 | $0.00 | $8,568.00 | |
0076 | (PL)REMOVE & RESET EXISTING SIGNS | 890A/B 8756 | EA | 6.000 | 6.000 | 14.000 | $50.00 | $0.00 | $700.00 | |
Subtotals For Category 0301/TRAFFIC - IM-STIM(011) | $0.00 | $23,178.50 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0600/STAKING - IM-STIM(011) | ||||||||
0077 | STAKING | 642 0098 | LSUM | 1.000 | 1.000 | 0.750 | $49,770.00 | $0.00 | $37,327.50 | |
Subtotals For Category 0600/STAKING - IM-STIM(011) | $0.00 | $37,327.50 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0640/CONSTRUCTION - IM-STIM(011) | ||||||||
0078 | (SP)SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.750 | $5,000.00 | $0.00 | $3,750.00 | |
0079 | FIELD OFFICE | 640 1398 | EA | 1.000 | 1.000 | 1.000 | $10,000.00 | $0.00 | $10,000.00 | |
0080 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $443,500.00 | $0.00 | $443,500.00 | |
0081 | (SP)CONTRACTORS QUALITY CONTROL | 643 0087 | LSUM | 1.000 | 1.000 | 0.750 | $60,000.00 | $0.00 | $45,000.00 | |
Subtotals For Category 0640/CONSTRUCTION - IM-STIM(011) | $0.00 | $502,250.00 | ||||||||
Fed/State Project Number: IM-STIM(011) | Project: 13626(06) | Category: 0850/Non ARRA Funding | ||||||||
8001 | (SP)ASPH.CONC.,TYPE S4(PATCH)(PG64-22OK) | 411(S4) 6310 | TON | 0.000 | 19.660 | 19.660 | $755.64 | $0.00 | $14,855.88 | |
8002 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 0.000 | 223.400 | 223.400 | $38.52 | $0.00 | $8,605.37 | |
8003 | MOBILIZATION | 641 1552 | LSUM | 0.000 | 1.000 | 1.000 | $5,250.00 | $0.00 | $5,250.00 | |
8004 | (PL)REMOVE AND RESET GUARD RAIL | 625(G) 1270 | LF | 0.000 | 4,000.000 | 3,700.500 | $11.50 | $0.00 | $42,555.75 | |
8005 | (PL)REMOVE & RESET G.E.T. G/ R END SECT. | 890A/B 8762 | EA | 0.000 | 10.000 | 6.000 | $551.25 | $0.00 | $3,307.50 | |
8006 | (SP)CEMENT KILN DUST | 327(B) 4210 | TON | 0.000 | 4,806.000 | 5,237.120 | $53.00 | $0.00 | $277,567.36 | |
8007 | CONCRETE PARAPET | 504(F) 1381 | LF | 0.000 | 295.800 | 295.800 | $66.88 | $0.00 | $19,783.10 | |
8008 | CONCRETE PARAPET | 504(F) 1381 | LF | 0.000 | 283.000 | 283.000 | $66.88 | $0.00 | $18,927.04 | |
8009 | GUARDRAIL DELINEATORS(TYPE 1, CODE 1) | 853 9066 | EA | 0.000 | 265.000 | 243.000 | 243.000 | $7.35 | $1,786.05 | $1,786.05 |
Subtotals For Category 0850/Non ARRA Funding | $1,786.05 | $392,638.05 | ||||||||
Subtotals For Project IM-STIM(011) /13626(06) | $3,985.80 | $9,695,025.10 |