| Fed/State Project Number: IM-STIM(011) |
Project: 13626(06) |
Category: 0100/ROADWAY - IM-STIM(011) |
| 0001 |
UNCLASSIFIED EXCAVATION |
202(A) 0183 |
CY |
40,024.000 |
40,024.000 |
7,000.000 |
11,434.640 |
$4.40 |
$30,800.00 |
$50,312.42 |
| 0002 |
UNCLASSIFIED BORROW |
202(C) 0184 |
CY |
15,531.000 |
15,531.000 |
2,300.000 |
7,614.830 |
$4.40 |
$10,120.00 |
$33,505.25 |
| 0003 |
TEMPORARY SILT FENCE |
223 2801 |
LF |
4,800.000 |
4,800.000 |
1,917.000 |
2,141.000 |
$2.00 |
$3,834.00 |
$4,282.00 |
| 0004 |
TEMPORARY SEDIMENT FILTER |
224 2803 |
EA |
5.000 |
5.000 |
|
0.000 |
$115.00 |
$0.00 |
$0.00 |
| 0005 |
TEMPORARY SILT DIKE |
227 0100 |
LF |
455.000 |
455.000 |
|
0.000 |
$9.00 |
$0.00 |
$0.00 |
| 0006 |
SOLID SLAB SODDING |
230(A) 2806 |
SY |
61,327.000 |
61,327.000 |
|
0.000 |
$1.50 |
$0.00 |
$0.00 |
| 0007 |
VEGETATIVE MULCHING |
233(A) 2817 |
AC |
12.670 |
12.670 |
|
0.000 |
$400.00 |
$0.00 |
$0.00 |
| 0008 |
MOWING |
241 2832 |
AC |
12.670 |
12.670 |
|
0.000 |
$49.00 |
$0.00 |
$0.00 |
| 0009 |
(SP)FLY ASH |
327(A) 4200 |
TON |
6,440.000 |
6,440.000 |
|
0.000 |
$45.00 |
$0.00 |
$0.00 |
| 0010 |
(SP)LIME |
327(D) 4230 |
TON |
217.000 |
217.000 |
|
0.000 |
$146.00 |
$0.00 |
$0.00 |
| 0011 |
(SP)CEMENTITIOUS STABILIZED SUBGRADE |
327(E) 4240 |
SY |
133,487.000 |
133,487.000 |
4,942.440 |
17,142.440 |
$2.65 |
$13,097.47 |
$45,427.47 |
| 0012 |
(SP)LIME PRETREATMENT |
327(G) 4260 |
SY |
21,432.000 |
21,432.000 |
1,558.440 |
1,558.440 |
$1.00 |
$1,558.44 |
$1,558.44 |
| 0013 |
TRAFFIC BOUND SURFACE COURSE TYPE E |
403(E) 0225 |
TON |
1,517.000 |
1,517.000 |
|
0.000 |
$28.00 |
$0.00 |
$0.00 |
| 0014 |
PRIME COAT |
408 5774 |
GAL |
20,219.000 |
20,219.000 |
|
0.000 |
$2.00 |
$0.00 |
$0.00 |
| 0015 |
(SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) |
411(S3) 5945 |
TON |
22,697.000 |
22,697.000 |
|
0.000 |
$61.60 |
$0.00 |
$0.00 |
| 0016 |
(SP)RUMBLE STRIP-METHOD PCC-CON |
413(D) 4868 |
LF |
52,235.000 |
52,235.000 |
|
0.000 |
$0.18 |
$0.00 |
$0.00 |
| 0017 |
(SP)P.C.CONCRETE PAVEMENT(PLACEMENT) |
414(A) 0210 |
SY |
57,956.000 |
57,956.000 |
|
22,989.710 |
$12.50 |
$0.00 |
$287,371.38 |
| 0018 |
(SP)DOWEL JOINTED P.C. CONCRETE PAVEMENT(PLACEMENT ) |
414(A1) 5725 |
SY |
76,264.000 |
76,264.000 |
|
0.000 |
$13.75 |
$0.00 |
$0.00 |
| 0019 |
(SP)P.C. CONCRETE FOR PAVEMENT |
414(P) 6000 |
CY |
43,522.000 |
43,522.000 |
0.000 |
5,146.720 |
$78.00 |
$0.00 |
$401,444.16 |
| 0020 |
COLD MILLING PAVEMENT |
417 5267 |
SY |
11,733.000 |
11,733.000 |
|
10,078.570 |
$3.98 |
$0.00 |
$40,112.71 |
| 0021 |
INLET (SMD-TYPE 1) |
611(E) 6000 |
EA |
4.000 |
4.000 |
|
0.000 |
$2,765.00 |
$0.00 |
$0.00 |
| 0022 |
24" R.C.PIPE CLASS III |
613(B) 0492 |
LF |
500.000 |
500.000 |
|
0.000 |
$51.00 |
$0.00 |
$0.00 |
| 0023 |
36" R.C.PIPE CLASS III |
613(B) 0494 |
LF |
100.000 |
100.000 |
|
0.000 |
$80.00 |
$0.00 |
$0.00 |
| 0024 |
TYPE B6 CULVERT END TREATMENT |
613(CC) 7197 |
EA |
2.000 |
2.000 |
|
0.000 |
$1,500.00 |
$0.00 |
$0.00 |
| 0025 |
TYPE D6 CULVERT END TREATMENT |
613(CC) 7199 |
EA |
4.000 |
4.000 |
|
0.000 |
$2,300.00 |
$0.00 |
$0.00 |
| 0026 |
6" PERFORATED PIPE UNDERDRAIN ROUND |
613(P) 1091 |
LF |
1,855.000 |
1,855.000 |
|
0.000 |
$10.00 |
$0.00 |
$0.00 |
| 0027 |
6" NON-PERF.PIPE UNDERDRAIN RND. |
613(Q) 1096 |
LF |
619.000 |
619.000 |
|
0.000 |
$10.00 |
$0.00 |
$0.00 |
| 0028 |
PIPE UNDERDRAIN COVER MAT'L. |
613(R) 1100 |
CY |
557.000 |
557.000 |
|
0.000 |
$25.00 |
$0.00 |
$0.00 |
| 0029 |
REMOVAL OF HEADWALL |
619(B) 0291 |
EA |
2.000 |
2.000 |
|
0.000 |
$1,260.00 |
$0.00 |
$0.00 |
| 0030 |
REMOVAL OF CONCRETE PAVEMENT |
619(B) 4727 |
SY |
122,783.000 |
122,783.000 |
29,877.330 |
29,877.330 |
$1.50 |
$44,816.00 |
$44,816.00 |
| 0031 |
REMOVAL OF ASPHALT PAVEMENT |
619(B) 4728 |
SY |
38,844.000 |
38,844.000 |
15,527.320 |
16,238.440 |
$1.50 |
$23,290.98 |
$24,357.66 |
| 0032 |
REMOVAL OF GUARD RAIL |
619(B) 4780 |
LF |
10,138.000 |
10,138.000 |
6,297.000 |
6,697.000 |
$1.55 |
$9,760.35 |
$10,380.35 |
| 0033 |
SAWING PAVEMENT |
619(C) 0924 |
LF |
20,094.000 |
20,094.000 |
|
0.000 |
$0.01 |
$0.00 |
$0.00 |
| 0034 |
BEAM GUARD RAIL-W-BEAM-SINGLE |
623(A) 0932 |
LF |
10,737.500 |
10,737.500 |
|
0.000 |
$14.37 |
$0.00 |
$0.00 |
| 0035 |
THRIE BEAM BRIDGE CONNECTION-TYPE A |
623(E) 7114 |
EA |
8.000 |
8.000 |
|
0.000 |
$2,060.00 |
$0.00 |
$0.00 |
| 0036 |
GUARD RAIL ANCHOR UNIT (TYPE B) |
623(F) 4447 |
EA |
24.000 |
24.000 |
|
0.000 |
$721.00 |
$0.00 |
$0.00 |
| 0037 |
(SP)G.E.T. GUARD RAIL END SECTION |
623(H) 8571 |
EA |
2.000 |
2.000 |
|
0.000 |
$3,090.00 |
$0.00 |
$0.00 |
| 8001 |
(SP)ASPH.CONC.,TYPE S4(PATCH)(PG64-22OK) |
411(S4) 6310 |
TON |
0.000 |
0.000 |
|
0.000 |
$755.64 |
$0.00 |
$0.00 |
| 8002 |
REMOVAL OF ASPHALT PAVEMENT |
619(B) 4728 |
SY |
0.000 |
0.000 |
|
0.000 |
$38.52 |
$0.00 |
$0.00 |
| 8003 |
MOBILIZATION |
641 1552 |
LSUM |
0.000 |
0.000 |
|
0.000 |
$5,250.00 |
$0.00 |
$0.00 |
| 8004 |
(PL)REMOVE AND RESET GUARD RAIL |
625(G) 1270 |
LF |
0.000 |
0.000 |
|
0.000 |
$11.50 |
$0.00 |
$0.00 |
| 8005 |
(PL)REMOVE & RESET G.E.T. G/ R END SECT. |
890A/B 8762 |
EA |
0.000 |
0.000 |
|
0.000 |
$551.25 |
$0.00 |
$0.00 |
| Subtotals For Category 0100/ROADWAY - IM-STIM(011) |
$137,277.24 |
$943,567.84 |
|
| Fed/State Project Number: IM-STIM(011) |
Project: 13626(06) |
Category: 0300/TRAFFIC SIGNING & STRIPING - IM-STIM(011) |
| 0054 |
RELOCATION OF RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN |
627(O) 4410 |
LF |
17,200.000 |
17,200.000 |
|
0.000 |
$2.50 |
$0.00 |
$0.00 |
| 0055 |
RENTED PORTABLE TYPE PRECAST CONCRETE MEDIAN BARRIER |
627(P) 4425 |
LF |
17,200.000 |
17,200.000 |
|
17,198.000 |
$29.65 |
$0.00 |
$509,920.70 |
| 0056 |
CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) |
856(A) 8839 |
LF |
54,000.000 |
54,000.000 |
|
71,128.000 |
$0.20 |
$0.00 |
$14,225.60 |
| 0057 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-1 |
856(G) 8887 |
EA |
7,890.000 |
7,890.000 |
|
0.000 |
$0.35 |
$0.00 |
$0.00 |
| 0058 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) |
859(A) 8006 |
LF |
34,500.000 |
34,500.000 |
|
17,906.000 |
$0.10 |
$0.00 |
$1,790.60 |
| 0059 |
(PL)CONST.ZONE IMPACT ATTEN. |
871 8705 |
SD |
900.000 |
900.000 |
|
0.000 |
$1.00 |
$0.00 |
$0.00 |
| 0060 |
MODULAR GLARE SCREEN |
878(C) 8487 |
SD |
17,100.000 |
17,100.000 |
1,650.000 |
1,760.000 |
$0.30 |
$495.00 |
$528.00 |
| 0061 |
ARROW DISPLAY(TYPE C) |
880(A) 8812 |
SD |
300.000 |
300.000 |
30.000 |
82.000 |
$22.00 |
$660.00 |
$1,804.00 |
| 0062 |
CONSTRUCTION SIGNS 0 TO 6.25 SF |
880(B) 8818 |
SD |
3,000.000 |
3,000.000 |
277.000 |
345.000 |
$0.90 |
$249.30 |
$310.50 |
| 0063 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF |
880(B) 8821 |
SD |
8,000.000 |
8,000.000 |
1,083.000 |
1,915.000 |
$1.25 |
$1,353.75 |
$2,393.75 |
| 0064 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF |
880(B) 8824 |
SD |
9,500.000 |
9,500.000 |
460.000 |
1,361.000 |
$0.35 |
$161.00 |
$476.35 |
| 0065 |
BARRICADES(TYPE III) |
880(C) 8842 |
SD |
5,500.000 |
5,500.000 |
360.000 |
450.000 |
$0.15 |
$54.00 |
$67.50 |
| 0066 |
WING BARRICADES |
880(C) 8848 |
SD |
600.000 |
600.000 |
60.000 |
164.000 |
$5.00 |
$300.00 |
$820.00 |
| 0067 |
VERTICAL PANELS |
880(D) 8854 |
SD |
41,500.000 |
41,500.000 |
4,470.000 |
4,768.000 |
$0.28 |
$1,251.60 |
$1,335.04 |
| 0068 |
WARNING LIGHTS(TYPE A) |
880(E) 8860 |
SD |
17,000.000 |
17,000.000 |
1,102.000 |
1,715.000 |
$0.03 |
$33.06 |
$51.45 |
| 0069 |
WARNING LIGHTS(TYPE C) |
880(E) 8872 |
SD |
58,500.000 |
58,500.000 |
1,740.000 |
2,828.000 |
$0.04 |
$69.60 |
$113.12 |
| 0070 |
DRUMS |
880(F) 8878 |
SD |
17,000.000 |
17,000.000 |
2,355.000 |
14,888.000 |
$0.40 |
$942.00 |
$5,955.20 |
| 0071 |
TRAFFIC SURVEILLANCE, POLICE |
880(L) 8911 |
HOUR |
600.000 |
600.000 |
|
170.000 |
$80.00 |
$0.00 |
$13,600.00 |
| 0072 |
PORT.CHANGEABLE MESSAGE SIGN |
882(B) 8306 |
SD |
600.000 |
600.000 |
|
0.000 |
$2.00 |
$0.00 |
$0.00 |
| Subtotals For Category 0300/TRAFFIC SIGNING & STRIPING - IM-STIM(011) |
$5,569.31 |
$553,391.81 |
|