Contract ID: | 090176 | Estimate Number: | 0004 | Contract No: | 411318 | |||
Residency: | ENID (04300) | Estimate Type: | Progressive | Account No: | 400400 | |||
Project Number(s): | NH-STIM(239)3R | ||||||||||||
Primary Job Piece No: | 26357(04) | ||||||||||||
Contract Description: | RESURFACE (ASPHALT) US-60: BEGIN AT THE MAJOR C/L, EXTEND EAST. PROJECT LENGTH = 5.00 MILES | ||||||||||||
Primary County: | GARFIELD | ||||||||||||
Name of Road: | US-60 | ||||||||||||
Prime Contractor: | THE CUMMINS CONSTRUCTION CO., INC. | ||||||||||||
P. O. BOX 748 | |||||||||||||
ENID , OK 73702 | |||||||||||||
Surety Company: | HARTFORD ACCIDENT & INDEMNITY COMPANY | ||||||||||||
Date Let: | 05/14/2009 | NTP Effective Date: | 10/30/2009 | Pay Period: | 09/01/2009 TO 09/15/2009 |
Date Awarded: | 05/19/2009 | Date Work Began: | 08/10/2009 | Original Contract Time: | N/A |
Date Contract Executed: | 06/01/2009 | Date Time Stopped: | Current Time Charged: | N/A | |
Date NTP Issued: | 06/05/2009 | Completion Date: | Current Time Allowed: | N/A | |
General Liability Expires: | 09/01/2010 | Workman's Comp Expires: | 01/01/1010 | Percent Time Used: | N/A |
Specification Year: | 1999 | FIXED COMPLETION DATE: | 10/31/2009 | Date Approved: | |
Current Contract Amount: | $2,739,321.18 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $2,739,321.18 | Participating: | $1,156,114.09 | $759,390.61 | $396,723.48 | ||
Percent Complete: | 42.20 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $1,583,207.09 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $1,583,207.09 | Total Earnings: | $1,156,114.09 | $759,390.61 | $396,723.48 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $1,156,114.09 | $759,390.61 | $396,723.48 | ||||
Other Adjustments: | $0.00 | $0.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $1,156,114.09 | $759,390.61 | $396,723.48 |
Contract ID: | 090176 | Estimate Number: | 0004 | Primary JP: | 26357(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Correction of contract to match plans | Pending | 0 | 0.0 | $0.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 090176 | Estimate Number: | 0004 | Primary JP: | 26357(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: NH-STIM(239)3R | Project: 26357(04) | Category: 0100/ROADWAY | ||||||||
0001 | UNCLASSIFIED BORROW (TOPSOIL) | 202(E) 4781 | CY | 1,000.000 | 1,000.000 | 0.000 | $14.20 | $0.00 | $0.00 | |
0002 | (SP)ASPHALT CONCRETE TYPE S3(PATCHING)(PG 64-22 OK) | 411(S3) 6210 | TON | 1,200.000 | 1,200.000 | 0.000 | $113.00 | $0.00 | $0.00 | |
0003 | (SP)ASPHALT CONCRETE TYPE S4(PG 70-28 OK) | 411(S4) 5955 | TON | 24,000.000 | 24,000.000 | 5,212.520 | 13,502.430 | $75.02 | $391,043.25 | $1,012,952.29 |
0004 | (SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 411(S4) 5960 | TON | 6,700.000 | 6,700.000 | 0.000 | $70.60 | $0.00 | $0.00 | |
0005 | RUMBLE STRIP-METHOD AC-CON | 413(A) 4861 | LF | 95,000.000 | 95,000.000 | 0.000 | $0.10 | $0.00 | $0.00 | |
0006 | COLD MILLING PAVEMENT | 417 5267 | SY | 190,000.000 | 190,000.000 | 4,403.030 | 141,150.660 | $0.92 | $4,050.79 | $129,858.61 |
0007 | REMOVAL OF CURB AND GUTTER | 619(B) 4726 | LF | 600.000 | 600.000 | 385.000 | $6.80 | $0.00 | $2,618.00 | |
0008 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 2,000.000 | 2,000.000 | 583.330 | $8.40 | $0.00 | $4,899.97 | |
850 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 0.000 | 0.000 | 0.000 | $8.40 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY | $395,094.04 | $1,150,328.87 | ||||||||
Fed/State Project Number: NH-STIM(239)3R | Project: 26357(04) | Category: 0300/TRAFFIC | ||||||||
0009 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 45.000 | 45.000 | 0.000 | $18.98 | $0.00 | $0.00 | |
0010 | 2" SQUARE TUBE POST | 851(C) 8324 | LF | 60.000 | 60.000 | 0.000 | $12.65 | $0.00 | $0.00 | |
0011 | 2 1/4" SQUARE TUBE POST | 851(C) 8327 | LF | 18.000 | 18.000 | 0.000 | $3.16 | $0.00 | $0.00 | |
0012 | BARRIER DELINEATORS(TYPE 1, CODE 1) | 853 9060 | EA | 84.000 | 84.000 | 0.000 | $3.40 | $0.00 | $0.00 | |
0013 | GUARDRAIL DELINEATORS(TYPE 1, CODE 1) | 853 9066 | EA | 200.000 | 200.000 | 0.000 | $7.00 | $0.00 | $0.00 | |
0014 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 855(A) 8812 | LF | 150,000.000 | 150,000.000 | 0.000 | $0.48 | $0.00 | $0.00 | |
0015 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 855(B) 8818 | EA | 56.000 | 56.000 | 0.000 | $73.80 | $0.00 | $0.00 | |
0016 | TRAFFIC STRIPE(PLASTIC)(WORDS) | 855(B) 8821 | EA | 21.000 | 21.000 | 0.000 | $79.10 | $0.00 | $0.00 | |
0017 | NONREMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 856(E) 8869 | LF | 2,700.000 | 2,700.000 | 0.000 | $5.55 | $0.00 | $0.00 | |
0018 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 4,000.000 | 4,000.000 | 0.000 | $0.05 | $0.00 | $0.00 | |
0019 | (PL)TRUCK MOUNTED ATTENUATOR | 876(C) 8482 | SD | 90.000 | 90.000 | 0.000 | $3.18 | $0.00 | $0.00 | |
0020 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 90.000 | 90.000 | 17.000 | 38.000 | $1.05 | $17.85 | $39.90 |
0021 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 1,000.000 | 1,000.000 | 442.000 | 956.000 | $0.65 | $287.30 | $621.40 |
0022 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 5,000.000 | 5,000.000 | 525.000 | 1,116.000 | $0.65 | $341.25 | $725.40 |
0023 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 5,000.000 | 5,000.000 | 913.000 | 1,855.000 | $0.45 | $410.85 | $834.75 |
0024 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 1,200.000 | 1,200.000 | 17.000 | $0.03 | $0.00 | $0.51 | |
0025 | WING BARRICADES | 880(C) 8848 | SD | 400.000 | 400.000 | 60.000 | 144.000 | $5.30 | $318.00 | $763.20 |
0026 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 7,400.000 | 7,400.000 | 615.000 | 1,425.000 | $0.03 | $18.45 | $42.75 |
0027 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 8,000.000 | 8,000.000 | 528.000 | 1,107.000 | $0.03 | $15.84 | $33.21 |
0028 | DRUMS | 880(F) 8878 | SD | 8,000.000 | 8,000.000 | 526.000 | 1,096.000 | $0.05 | $26.30 | $54.80 |
0029 | CONES(36" LARGE) | 880(H) 8896 | SD | 30,000.000 | 30,000.000 | 2,912.000 | 5,187.000 | $0.05 | $145.60 | $259.35 |
0030 | PORT.CHANGEABLE MESSAGE SIGN | 882(B) 8306 | SD | 90.000 | 90.000 | 15.000 | 25.000 | $3.20 | $48.00 | $80.00 |
0031 | (PL)REMOVAL OF CLASS C PAVEMENT MARKERS | 890(A) 8702 | EA | 200.000 | 200.000 | 147.000 | $15.85 | $0.00 | $2,329.95 | |
Subtotals For Category 0300/TRAFFIC | $1,629.44 | $5,785.22 | ||||||||
Fed/State Project Number: NH-STIM(239)3R | Project: 26357(04) | Category: 0850/Non ARRA Funding | ||||||||
Subtotals For Category 0850/Non ARRA Funding | $0.00 | $0.00 | ||||||||
Subtotals For Project NH-STIM(239)3R /26357(04) | $396,723.48 | $1,156,114.09 |