Contract ID: | 090125 | Estimate Number: | 0004 | Contract No: | ||||
Residency: | COBB ENGINEERING CO., INC. (04003) | Estimate Type: | Progressive | Account No: | ||||
Project Number(s): | IM-STIM(177)3R | ||||||||||||
Primary Job Piece No: | 26281(04) | ||||||||||||
Contract Description: | PAVEMENT REHAB (DOWEL RETROFIT) I-235: BEGIN AT NORTH END OF OKLAHOMA RIVER BRIDGE, EXTEND NORTH. PROJECT LENGTH = 3.47 MILES | ||||||||||||
Primary County: | OKLAHOMA | ||||||||||||
Name of Road: | I-235 | ||||||||||||
Prime Contractor: | PENHALL COMPANY | ||||||||||||
1801 PENHALL WAY | |||||||||||||
ANAHEIM , CA 92801 | |||||||||||||
Surety Company: | SAFECO INSURANCE COMPANY | ||||||||||||
Date Let: | 03/24/2009 | NTP Effective Date: | 04/27/2009 | Pay Period: | 07/01/2009 TO 07/15/2009 |
Date Awarded: | 03/30/2009 | Date Work Began: | 05/18/2009 | Original Contract Time: | 90 |
Date Contract Executed: | 04/10/2009 | Date Time Stopped: | Current Time Charged: | 80.00 | |
Date NTP Issued: | 04/13/2009 | Completion Date: | Current Time Allowed: | 108.00 | |
General Liability Expires: | 07/01/2010 | Workman's Comp Expires: | 07/01/2010 | Percent Time Used: | 74.07 % |
Specification Year: | 1999 | Date Approved: | |||
Current Contract Amount: | $2,665,320.00 | Total to Date | Prev to Date | This Estimate | |||
Bid Amount: | $2,665,320.00 | Participating: | $1,543,862.43 | $1,133,430.92 | $410,431.51 | ||
Percent Complete: | 57.74 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Funds Available: | $1,126,457.57 | Non ARRA: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $1,126,457.57 | Total Earnings: | $1,543,862.43 | $1,133,430.92 | $410,431.51 | ||
Stockpiled Materials: | $0.00 | $0.00 | $0.00 | ||||
Gross Earnings: | $1,543,862.43 | $1,133,430.92 | $410,431.51 | ||||
Other Adjustments: | $-5,000.00 | $-5,000.00 | $0.00 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $1,538,862.43 | $1,128,430.92 | $410,431.51 |
Contract ID: | 090125 | Estimate Number: | 0004 | Primary JP: | 26281(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Revise SP 108-STIM01 | Approved | 06/11/2009 | 0.0 | $0.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
No material stockpiles have been created for this contract. | Subtotals For Stockpile Payments | $0.00 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
Lane Rental | 0003 | $-5,000.00 | Subtotals For Contract Adjustments | $-5,000.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
No line item adjustments have been created on this contract. | Subtotals For Line Item Adjustments | $0.00 |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Description | Time Allowed | Time Used | Rate | Total | ||||
No milestones exist for this contract. |
Contract ID: | 090125 | Estimate Number: | 0004 | Primary JP: | 26281(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: IM-STIM(177)3R | Project: 26281(04) | Category: 0100/ROADWAY | ||||||||
0001 | AGGREGATE BASE | 303 0192 | CY | 100.000 | 100.000 | 50.200 | 269.200 | $25.00 | $1,255.00 | $6,730.00 |
0002 | 9" H.E.S. DOWEL JOINTED CONCRETE PAVEMENT | 414(B1) 5758 | SY | 2,500.000 | 2,500.000 | 227.170 | 2,086.850 | $136.00 | $30,895.12 | $283,811.60 |
0003 | APPROACH SLABS | 414(C) 0309 | SY | 2,900.000 | 2,900.000 | 363.500 | 1,593.870 | $231.00 | $83,968.50 | $368,183.97 |
0004 | CONCRETE JOINT REHABILITATION | 419 4152 | LF | 160,000.000 | 160,000.000 | 0.000 | $0.81 | $0.00 | $0.00 | |
0005 | DIAMOND GRINDING CONCRETE PAVEMENT | 425 5195 | SY | 85,000.000 | 85,000.000 | 21,109.340 | 21,109.340 | $2.50 | $52,773.35 | $52,773.35 |
0006 | POLYURETHANE INJECTION FOR PAVEMENT | 426(D) 6010 | LB | 16,000.000 | 16,000.000 | 11,476.000 | 38,251.000 | $4.25 | $48,773.00 | $162,566.75 |
0007 | DOWEL BAR RETROFIT | 436 0100 | EA | 24,000.000 | 24,000.000 | 4,902.000 | 10,944.000 | $26.00 | $127,452.00 | $284,544.00 |
0008 | STRUCTURAL STEEL | 506(A) 1322 | LB | 2,000.000 | 2,000.000 | 0.000 | 182.000 | $0.75 | $0.00 | $136.50 |
0009 | EPOXY COATED REINFORCING STEEL | 511(B) 4269 | LB | 24,000.000 | 24,000.000 | 31,835.000 | 121,691.000 | $0.75 | $23,876.25 | $91,268.25 |
0010 | REMOVAL OF CONCRETE PAVEMENT | 619(B) 4727 | SY | 2,500.000 | 2,500.000 | 227.170 | 2,086.850 | $39.00 | $8,859.63 | $81,387.15 |
0011 | REMOVAL OF EXISTING SLAB | 619(B) 6189 | SY | 2,900.000 | 2,900.000 | 363.500 | 1,593.870 | $52.00 | $18,902.00 | $82,881.24 |
Subtotals For Category 0100/ROADWAY | $396,754.85 | $1,414,282.81 | ||||||||
Fed/State Project Number: IM-STIM(177)3R | Project: 26281(04) | Category: 0300/TRAFFIC | ||||||||
0012 | (SP)TRAFFIC STRIPE(MULTI-POLYMER) | 854(C) 8520 | LF | 230,000.000 | 230,000.000 | 0.000 | $0.52 | $0.00 | $0.00 | |
0013 | (SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | 854(C) 8525 | EA | 100.000 | 100.000 | 0.000 | $250.00 | $0.00 | $0.00 | |
0014 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 859(A) 8006 | LF | 70,000.000 | 70,000.000 | 0.000 | $0.50 | $0.00 | $0.00 | |
0015 | (PL)TRUCK MOUNTED ATTENUATOR | 876(C) 8482 | SD | 180.000 | 180.000 | 23.000 | 95.000 | $4.00 | $92.00 | $380.00 |
0016 | ARROW DISPLAY(TYPE C) | 880(A) 8812 | SD | 200.000 | 200.000 | 23.000 | 95.000 | $9.00 | $207.00 | $855.00 |
0017 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 3,000.000 | 3,000.000 | 360.000 | 1,394.000 | $0.40 | $144.00 | $557.60 |
0018 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 8,000.000 | 8,000.000 | 135.000 | 350.000 | $0.02 | $2.70 | $7.00 |
0019 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 8,000.000 | 8,000.000 | 480.000 | 1,774.000 | $0.02 | $9.60 | $35.48 |
0020 | BARRICADES(TYPE III) | 880(C) 8842 | SD | 1,000.000 | 1,000.000 | 41.000 | 221.000 | $0.02 | $0.82 | $4.42 |
0021 | WING BARRICADES | 880(C) 8848 | SD | 240.000 | 240.000 | 41.000 | 221.000 | $2.00 | $82.00 | $442.00 |
0022 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 9,000.000 | 9,000.000 | 448.000 | 2,266.000 | $0.02 | $8.96 | $45.32 |
0023 | WARNING LIGHTS(TYPE C) | 880(E) 8872 | SD | 20,000.000 | 20,000.000 | 298.000 | 1,481.000 | $0.02 | $5.96 | $29.62 |
0024 | DRUMS | 880(F) 8878 | SD | 20,000.000 | 20,000.000 | 901.000 | 4,079.000 | $0.02 | $18.02 | $81.58 |
0025 | CONES(36" LARGE) | 880(H) 8896 | SD | 20,000.000 | 20,000.000 | 2,124.000 | 10,114.000 | $0.90 | $1,911.60 | $9,102.60 |
0026 | TRAFFIC SURVEILLANCE, POLICE | 880(L) 8911 | HOUR | 800.000 | 800.000 | 162.000 | 616.000 | $67.00 | $10,854.00 | $41,272.00 |
0027 | PORT.CHANGEABLE MESSAGE SIGN | 882(B) 8306 | SD | 300.000 | 300.000 | 20.000 | 77.000 | $1.00 | $20.00 | $77.00 |
0028 | (PL)REMOVAL OF CLASS C PAVEMENT MARKERS | 890(A) 8702 | EA | 1,900.000 | 1,900.000 | 32.000 | 169.000 | $10.00 | $320.00 | $1,690.00 |
Subtotals For Category 0300/TRAFFIC | $13,676.66 | $54,579.62 | ||||||||
Fed/State Project Number: IM-STIM(177)3R | Project: 26281(04) | Category: 0640/CONSTRUCTION | ||||||||
0029 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 1.000 | $75,000.00 | $0.00 | $75,000.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $75,000.00 | ||||||||
Fed/State Project Number: IM-STIM(177)3R | Project: 26281(04) | Category: 0850/Non ARRA Funding | ||||||||
Subtotals For Category 0850/Non ARRA Funding | $0.00 | $0.00 | ||||||||
Subtotals For Project IM-STIM(177)3R /26281(04) | $410,431.51 | $1,543,862.43 |